CCNA Project Life Cycle Questions

13 of 88 questions · Page 2/2 · Project Life Cycle topic · Answers revealed

76
MCQhard

A project is in the execution phase, developing a mobile payment application. The project manager receives a report that a critical security vulnerability was discovered in the third-party authentication library used by the application. The library is widely used and has an available patch that requires upgrading to a newer version. However, upgrading the library will break compatibility with the existing user authentication database schema, requiring a database migration that was not planned. The project has a fixed budget and a tight deadline. The change control board (CCB) meets weekly, and the next meeting is in three days. The lead developer recommends applying the patch immediately without waiting for CCB approval, arguing that the security risk is high and the patch is straightforward. What is the BEST course of action for the project manager?

A.Escalate the issue to the project sponsor to decide on an exception to the change control process
B.Apply the patch immediately and inform the CCB after the fact, as security vulnerabilities require urgent action
C.Do not implement the patch because the project is on a tight schedule and the risk is acceptable
D.Wait for the next CCB meeting to present the issue and get approval for the upgrade and database migration
AnswerD

This follows the change control process and ensures proper assessment and approval.

Why this answer

Option D is correct because the project manager must follow the established change control process, even for urgent security patches, when the change introduces an unplanned database migration that impacts scope, budget, and schedule. Waiting for the next CCB meeting (in three days) allows proper assessment of the upgrade's impact on the authentication database schema and ensures all stakeholders approve the change. Applying the patch without approval violates the change management plan and could lead to uncontrolled scope creep and budget overruns.

Exam trap

The trap here is that candidates assume security vulnerabilities always justify bypassing change control, but the PM must balance urgency with process, especially when the patch introduces an unplanned database migration that affects the fixed budget and tight deadline.

How to eliminate wrong answers

Option A is wrong because escalating to the project sponsor bypasses the CCB's authority and the defined change control process; the sponsor is not typically empowered to grant exceptions for technical changes that affect the database schema. Option B is wrong because applying the patch immediately without CCB approval violates the change management plan, and the security vulnerability does not justify breaking the process when a CCB meeting is only three days away. Option C is wrong because dismissing the patch as acceptable risk ignores the critical security vulnerability in a widely used authentication library, which could lead to data breaches and compliance violations.

77
Matchingmedium

Match each quality management concept to its definition.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Process-oriented activities to ensure quality standards are met

Product-oriented activities to verify deliverables meet requirements

Keeping errors out of the process

Checking deliverables for defects

Ongoing effort to improve products, services, or processes

Why these pairings

These concepts are fundamental to project quality management.

78
Multi-Selectmedium

Which TWO activities are typically performed during the initiation phase of a project?

Select 2 answers
A.Develop the project charter
B.Develop the project schedule
C.Identify stakeholders
D.Develop the work breakdown structure
E.Create the risk response plan
AnswersA, C

Part of initiation.

Why this answer

Options C and D are correct. The initiation phase includes identifying stakeholders and developing the project charter. Option A is incorrect because the WBS is created in planning.

Option B is incorrect because the risk response plan is created in planning. Option E is incorrect because the schedule is developed in planning.

79
MCQhard

A large software development project is using a waterfall life cycle. The project has just completed the design phase, and the project manager is scheduled to conduct a phase gate review before proceeding to coding. The project sponsor, under pressure from upper management to deliver faster, asks the project manager to skip the gate review to save one week and move directly to coding. The sponsor argues that the design is sound and the review is a formality. What should the project manager do?

A.Escalate the issue to the program manager without further discussion.
B.Agree to skip the review to meet the sponsor's timeline.
C.Document the sponsor's request and proceed with coding.
D.Explain the purpose of the gate review and proceed with it to ensure quality and risk mitigation.
AnswerD

Maintains governance and project integrity.

Why this answer

The correct action is to explain the importance of the gate review and insist on conducting it as planned, because phase gates ensure quality and risk mitigation. Option A is correct because skipping gates can lead to unrecognized issues and project failure. Option B is wrong as it violates the defined process and best practices.

Option C is wrong because escalating prematurely may damage relationships; the PM should first explain. Option D is wrong because it abdicates the PM's responsibility.

80
MCQmedium

During project planning, the project manager wants to ensure that all work is defined and that no work is omitted. Which tool or technique should be used?

A.Responsibility assignment matrix
B.Gantt chart
C.Network diagram
D.Work breakdown structure (WBS)
AnswerD

The WBS decomposes the project scope into manageable work packages and ensures all work is captured.

Why this answer

The work breakdown structure is the primary tool for ensuring all work is identified and organized.

81
MCQhard

A project is in execution when a critical vendor fails to deliver a key component. The project manager determines this will push the project past the deadline. After submitting a change request, what should the project manager do next?

A.Fast track the remaining tasks
B.Communicate the impact to stakeholders
C.Request additional resources
D.Update the risk register
AnswerB

Stakeholders need to be informed of the potential delay and the submitted change request as soon as possible.

Why this answer

After submitting a change request, the project manager should communicate the potential impact to stakeholders to manage expectations. Updating the risk register is important but not the immediate next step; fast tracking and requesting resources may be considered after approval.

82
MCQeasy

During a project's executing phase, a key team member requests a change to the project scope. What should the project manager do first?

A.Submit the change request to the change control board
B.Reject the change to avoid scope creep
C.Update the project management plan directly
D.Approve the change immediately to maintain team morale
AnswerA

A formal change request should be submitted for evaluation.

Why this answer

Following the change control process, the first step is to submit a formal change request, which will then be evaluated by the change control board.

83
MCQhard

A project is in execution, and the project manager discovers that a key resource is overallocated. Which of the following actions should the project manager take to resolve this?

A.Add more resources
B.Outsource the work
C.Apply resource leveling
D.Reduce project scope
AnswerC

Resource leveling adjusts the schedule to resolve overallocation without adding resources.

Why this answer

Resource leveling is a technique to address resource overallocation by delaying tasks within their float.

84
MCQhard

You are managing a software development project with a fixed deadline. The project team consists of 10 developers and 2 testers. The project is currently in the execution phase. During a status review, you find that one of the critical path tasks is two weeks behind schedule due to a key developer being reassigned to another project. The product owner is unwilling to reduce scope. The project sponsor has instructed you to bring the schedule back on track without increasing the budget. The project plan does not include any contingency time. Which of the following is the best course of action?

A.Request a schedule extension from the sponsor
B.Reassign a developer from a non-critical task to the critical task
C.Ask the team to work overtime
D.Add more developers to the task
AnswerB

This uses existing resources without additional cost and can bring the critical path back on track by focusing effort on the delayed task.

Why this answer

Reassigning a developer from a non-critical task (which has float) to the critical path task is the most cost-effective way to recover schedule without additional budget or scope changes.

85
MCQhard

You are a project manager for a construction project. During the monitoring and controlling phase, you review the project performance and find that the earned value (EV) is $50,000, the actual cost (AC) is $60,000, and the planned value (PV) is $55,000. The project is behind schedule and over budget. The project team is demotivated due to the delays. The customer has expressed concerns about project progress. The project contract includes a penalty clause for missed milestones. Which of the following actions should you take first?

A.Implement additional quality control measures
B.Request a change order to increase the budget
C.Conduct a root cause analysis to identify reasons for variances
D.Immediately notify the customer about the delays
AnswerC

Understanding why the project is over budget and behind schedule is critical before taking corrective action.

Why this answer

Root cause analysis is the first step in addressing performance variances. Once the causes are known, the project manager can develop an appropriate corrective action plan.

86
MCQeasy

A project manager is planning a software development project and needs to determine the sequence of activities. The team will first gather requirements, then design the architecture, then develop the code, then test, and finally deploy. Which project life cycle model is being used?

A.Iterative
B.Agile
C.Waterfall
D.Spiral
AnswerC

Waterfall is linear and sequential, with phases completed one after another.

Why this answer

The Waterfall model (Option C) is correct because it follows a strictly sequential, phase-by-phase progression: requirements, design, development, testing, and deployment, with no overlap or iteration. This linear approach is characteristic of the Waterfall life cycle, where each phase must be completed before the next begins, as described in the PMBOK Guide for predictive life cycles.

Exam trap

The trap here is that candidates confuse the sequential phase names with Agile or Iterative terminology, forgetting that Waterfall is defined by its strict linearity and lack of overlapping phases or feedback cycles.

How to eliminate wrong answers

Option A is wrong because the Iterative model involves repeating cycles of development and refinement, not a single sequential pass through phases. Option B is wrong because Agile uses time-boxed iterations (sprints) with continuous feedback and incremental delivery, not a rigid linear sequence. Option D is wrong because the Spiral model combines iterative development with risk analysis in each cycle, not a straightforward sequential flow.

87
MCQmedium

During the planning phase, a project manager conducts a stakeholder analysis. Which of the following is the primary purpose of this activity?

A.To identify potential risks that stakeholders might introduce
B.To assign team members to project tasks
C.To define the project scope and deliverables
D.To identify and categorize stakeholders based on their interest and influence
AnswerD

Primary purpose of stakeholder analysis.

Why this answer

Option A is correct because stakeholder analysis identifies stakeholders' interests, influence, and expectations to manage them effectively. Option B is incorrect because stakeholder analysis is not about identifying project risks directly. Option C is incorrect because it does not define project scope.

Option D is incorrect because it does not assign tasks.

88
MCQeasy

A project manager is identifying stakeholders and documenting their interests and influence. In which project life cycle phase is this activity performed?

A.Executing
B.Initiating
C.Closing
D.Planning
AnswerB

Identifying stakeholders is part of the Initiating phase.

Why this answer

Identifying stakeholders is a key activity in the Initiating phase, where the project is formally authorized and stakeholders are identified.

← PreviousPage 2 of 2 · 88 questions total

Ready to test yourself?

Try a timed practice session using only Project Life Cycle questions.