Courseiva
Knowledge + Practice
CertificationsVendorsCareer RoadmapsLabs & ToolsStudy GuidesGlossaryPractice Questions
C
Courseiva

Free IT certification practice questions with explained answers for CCNA, CompTIA, AWS, Azure, Google Cloud, and more.

Certification Practice Questions

CCNA practice questionsSecurity+ SY0-701 practice questionsAWS SAA-C03 practice questionsAZ-104 practice questionsAZ-900 practice questionsCLF-C02 practice questionsA+ Core 1 practice questionsGoogle Cloud ACE practice questionsCySA+ CS0-003 practice questionsNetwork+ N10-009 practice questions
View all certifications →

Product

CertificationsCertification PathsExam TopicsPractice TestsExam Dumps vs Practice TestsStudy HubComparisons

Company

AboutContactEditorial PolicyQuestion Writing PolicyTrust Center

Legal

Privacy PolicyTerms of Service

Courseiva is a free IT certification practice platform offering original exam-style practice questions, detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics for Cisco, CompTIA, Microsoft, AWS, and other technology certifications.

© 2026 Courseiva. Courseiva is operated by JTNetSolutions Ltd. All rights reserved.

Courseiva is an independent certification practice platform and is not affiliated with, endorsed by, or sponsored by Cisco, Microsoft, AWS, CompTIA, Google, ISC2, ISACA, or any other certification vendor. Vendor names and certification marks are used only to identify the exams learners are preparing for.

HomeCertificationsPK0-005TopicsProject Life Cycle Phases
Free · No Signup RequiredCompTIA · PK0-005

PK0-005 Project Life Cycle Phases Practice Questions

20+ practice questions focused on Project Life Cycle Phases — one of the most tested topics on the CompTIA Project+ PK0-005 exam. Each question includes a detailed explanation so you learn why the right answer is correct.

Start Project Life Cycle Phases Practice

Exam Domains

Project Life Cycle PhasesBasics of IT Infrastructure and IT Project ManagementProject Management ConceptsTools and DocumentationAll domains →

Study Tools

Practice TestMock ExamFlashcardsAll Topics

Sample Project Life Cycle Phases Questions

Practice all 20+ →
1.

A project manager is reviewing lessons learned from a previous project and notices that scope creep occurred because stakeholders requested changes after the project moved into the execution phase. Which action should the project manager take in the current project to prevent this issue?

A.Close the project early if any scope changes are requested.
B.Involve all stakeholders in the project planning phase to ensure requirements are fully captured.
C.Include a detailed list of all deliverables in the project charter to avoid ambiguity.
D.Establish a change control board during the planning phase to review and approve any change requests.

Explanation: Option D is correct because establishing a change control board (CCB) during the planning phase provides a formal, documented process for reviewing and approving or rejecting scope changes. This prevents uncontrolled scope creep by ensuring that any change request is evaluated for impact on cost, schedule, and resources before implementation, which is a key practice in the PMBOK Guide for the execution phase.

2.

During the execution phase, a project manager discovers that the development team has been using an unauthorized software library to accelerate work. The library has a license that could create legal risks for the company. What is the best course of action?

A.Document the issue in the lessons learned and continue with the library to avoid delay.
B.Immediately stop using the library, assess the impact on the schedule, and develop a plan to replace it.
C.Continue using the library but add a note in the risk register about potential licensing issues.
D.Escalate the issue to the project sponsor and request a decision on whether to continue using the library.

Explanation: Option B is correct because using an unauthorized software library with a license that creates legal risks must be stopped immediately to protect the company from potential litigation. The project manager must then assess the schedule impact and develop a replacement plan, as continuing use without addressing the legal risk violates compliance and project governance standards.

3.

A project manager is planning a software development project and needs to determine the sequence of activities. The team will first gather requirements, then design the architecture, then develop the code, then test, and finally deploy. Which project life cycle model is being used?

A.Iterative
B.Agile
C.Waterfall
D.Spiral

Explanation: The Waterfall model (Option C) is correct because it follows a strictly sequential, phase-by-phase progression: requirements, design, development, testing, and deployment, with no overlap or iteration. This linear approach is characteristic of the Waterfall life cycle, where each phase must be completed before the next begins, as described in the PMBOK Guide for predictive life cycles.

4.

A project is in the execution phase, and the project manager receives a change request to add a new feature that is not in the scope statement. The change request has been approved by the change control board. What must the project manager do next?

A.Conduct a meeting with stakeholders to discuss the impact of the change.
B.Update the project management plan and baseline to reflect the approved change.
C.Defer the change to the next project phase to minimize disruption.
D.Inform the development team to continue with the original scope and ignore the change.

Explanation: Once the change control board (CCB) approves a change request, the project manager must formally integrate the approved change into the project by updating the project management plan and the associated baselines (scope, schedule, cost). This ensures that all future project work, performance measurement, and reporting are aligned with the new approved scope, maintaining the integrity of the project's control processes as defined in the PMBOK Guide.

5.

A project manager is creating a work breakdown structure (WBS) during the planning phase. The WBS should decompose the project deliverables into smaller, manageable components. What is the lowest level of a WBS called?

A.Planning package
B.Work package
C.Control account
D.Activity

Explanation: The lowest level of a work breakdown structure (WBS) is the work package, which represents the smallest unit of work that can be reliably estimated, assigned, and managed. Decomposing deliverables into work packages enables precise cost, resource, and schedule planning during the project planning phase.

+15 more Project Life Cycle Phases questions available

Practice all Project Life Cycle Phases questions

How to master Project Life Cycle Phases for PK0-005

1. Baseline your knowledge

Start with 10 questions to gauge your current understanding of Project Life Cycle Phases. This tells you whether you need a concept refresher or just practice.

2. Review every explanation

For each question — right or wrong — read the full explanation. Understanding why an answer is correct is more valuable than knowing the answer itself.

3. Focus on exam traps

Project Life Cycle Phases questions on the PK0-005 frequently use trap wording. Look for subtle differences in answers that test your precision, not just general knowledge.

4. Reach 80% consistently

Do repeated sessions until you score 80%+ three times in a row. Then move to mixed-mode practice to test cross-topic recall under realistic conditions.

Frequently asked questions

How many PK0-005 Project Life Cycle Phases questions are on the real exam?

The exact number varies per candidate. Project Life Cycle Phases is tested as part of the CompTIA Project+ PK0-005 blueprint. Practicing with targeted Project Life Cycle Phases questions ensures you can handle any format or difficulty that appears.

Are these PK0-005 Project Life Cycle Phases practice questions free?

Yes. Courseiva provides free PK0-005 practice questions across all exam topics and domains. The platform includes topic-based practice, mock exams, missed-question review, bookmarked questions, and readiness tracking — no account required.

Is Project Life Cycle Phases one of the harder PK0-005 topics?

Difficulty is subjective, but Project Life Cycle Phases is a high-priority exam concept tested in multiple ways — direct recall, scenario analysis, and command-output interpretation. Consistent practice is the best way to build confidence.

Ready to practice?

Launch a full Project Life Cycle Phases practice session with instant scoring and detailed explanations.

Start Project Life Cycle Phases Practice →

Topic Info

Topic

Project Life Cycle Phases

Exam

PK0-005

Questions available

20+