PK0-005 Practice Question: Refer to the exhibit

Exhibit

Risk Register:
ID: R001
Description: Potential vendor delay
Probability: High
Impact: High
Risk Score: 9
Response: Mitigate
Owner: PM

Refer to the exhibit. Based on the exhibit, which response strategy is the project manager planning to use for this risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Mitigate

The exhibit explicitly shows 'Response: Mitigate'. Options B, C, and D are incorrect as the response is clearly stated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Mitigate

    Why this is correct

    The response field states 'Mitigate'.

  • Transfer

    Why it's wrong here

    Transfer is not the chosen response.

  • Avoid

    Why it's wrong here

    Avoid is not indicated; the response is mitigate.

  • Accept

    Why it's wrong here

    Acceptance is not listed.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.