Match each project management tool or technique to its purpose.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Visual timeline of project tasks and dependencies

Hierarchical decomposition of project deliverables

Determines the longest sequence of dependent tasks

Measures project performance against baseline

Assigns roles: Responsible, Accountable, Consulted, Informed

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Gantt chart: Displays project tasks against a timeline

Correct matches: Gantt chart visualizes tasks over time; PERT chart shows dependencies and critical path; WBS breaks down deliverables. Common confusions arise because both Gantt and PERT are scheduling tools but serve different visual purposes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Gantt chart: Displays project tasks against a timeline

    Why this is correct

    A Gantt chart is a bar chart that illustrates a project schedule, showing tasks on the vertical axis and time on the horizontal axis.

  • PERT chart: Shows task dependencies and critical path

    Why this is correct

    A PERT chart is a network diagram that displays the sequence of tasks, dependencies, and the critical path for project scheduling.

  • Work Breakdown Structure: Hierarchical decomposition of project deliverables

    Why this is correct

    A WBS is a deliverable-oriented decomposition of the work required to complete the project, breaking it into smaller components.

  • Gantt chart: Shows task dependencies and critical path

    Why it's wrong here

    Incorrect — task dependencies and critical path are typically shown in network diagrams like PERT or CPM, not in a Gantt chart.

  • PERT chart: Displays project tasks against a timeline

    Why it's wrong here

    Incorrect — displaying tasks against a timeline is the purpose of a Gantt chart, not a PERT chart.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.