Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: During project planning, the team identifies high…

During project planning, the team identifies high uncertainty that could affect the schedule. Which document should the project manager create or update?

⚠ Common exam trap

It's easy for candidates to confuse the risk management plan with the risk register or assume that uncertainty is handled by updating the project charter, but the charter only authorizes the project and does not contain detailed risk response planning.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk management plan

The risk management plan is the correct document to create or update when high uncertainty could affect the schedule because it defines how risks will be identified, analyzed, responded to, and monitored throughout the project. This plan includes the risk register and risk response strategies, which directly address schedule uncertainties by establishing a structured approach to handling potential impacts. In the PK0-005 context, the risk management plan is a key component of the project management plan that proactively manages uncertainty rather than reacting after the fact.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Change log

    Why it's wrong here

    The change log records approved changes; it is not used to plan for uncertainty.

  • Lessons learned

    Why it's wrong here

    Lessons learned are documented during project closure, not during planning.

  • Risk management plan

    Why this is correct

    The risk management plan defines how to handle risks; it should be created during planning to address uncertainty.

  • Project charter

    Why it's wrong here

    The project charter formally authorizes the project; it is created during initiation, not updated for risk responses.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.