During project execution, a key stakeholder requests a change that increases scope. According to the project management plan, which document should the project manager update first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Change log

The change log is the document that records all change requests and their status, including scope changes. According to the project management plan, the change log should be updated first when a change request is submitted, before any other planning documents. Option A (project schedule) is updated only after the change is approved and the schedule impact is assessed. Option B (issue log) is for tracking issues, not changes. Option C (risk register) is for risks, not changes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project schedule

    Why it's wrong here

    Schedule updates occur after approval.

  • Issue log

    Why it's wrong here

    Issue log is for issues, not changes.

  • Risk register

    Why it's wrong here

    Risk register is for risks.

  • Change log

    Why this is correct

    Correct. The change log documents all change requests.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.