A project has the following activities and dependencies: A (5 days), B (3 days, after A), C (4 days, after A), D (2 days, after B), E (6 days, after C), F (1 day, after D and E). What is the total float of activity C?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

0 days

The critical path is A-C-E-F: 5+4+6+1=16 days. The path A-B-D-F: 5+3+2+1=11 days. The float for C is the difference between early start and late start. Since C is on the critical path, its total float is 0.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 0 days

    Why this is correct

    Critical path activities have zero float.

  • 1 day

    Why it's wrong here

    Incorrect calculation.

  • 2 days

    Why it's wrong here

    2 days is the float for activity B, not C.

  • 5 days

    Why it's wrong here

    5 days is the duration of A, not float.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.