PRINCE2-PRACTITIONER Processes Practice Question
Which THREE of the following inputs are required when executing the Initiating a Project (IP) process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Project Mandate
Key inputs to IP include the Project Brief (from SU), the Project Mandate, and guidance from Directing a Project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Project Mandate
Why this is correct
The original mandate provides initial context and direction.
- ✓
Direction from the Project Board (via DP)
Why this is correct
The Project Board authorizes and directs the initiation activity.
- ✗
Completed Work Package delivery sign-offs
Why it's wrong here
Work packages have not yet been executed during initiation.
- ✓
The Project Brief
Why this is correct
The Project Brief produced in SU is a primary input to IP.
- ✗
The End Project Report from the previous project
Why it's wrong here
End project reports from unrelated projects are not direct inputs to IP.
About these practice questions
One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint
This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.