A PRINCE2 project is executing its final stage. During the Closing a Project process, the Project Manager prepares the End Project Report. A key stakeholder demands that the project remain open for another three months to support post-project user adoption. According to PRINCE2, how should this be handled?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Proceed with project closure, handing over operational user adoption responsibilities to operational management as outlined in the Benefits Management Approach.

Projects deliver outputs, while operations realize benefits and handle ongoing user adoption post-project. Project closure should proceed as planned, with adoption support handed over to operational management.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Transfer project executive accountability to the Senior User and keep the project open.

    Why it's wrong here

    Project governance roles dissolve upon project closure.

  • Reject project closure and rewrite the PID into a new Stage Plan.

    Why it's wrong here

    Rewriting the PID at the end of a project is incorrect governance practice.

  • Proceed with project closure, handing over operational user adoption responsibilities to operational management as outlined in the Benefits Management Approach.

    Why this is correct

    Projects close once outputs are delivered; ongoing adoption and benefits realization are operational responsibilities.

  • Extend the project duration by three months to manage user adoption.

    Why it's wrong here

    Extending projects for post-project operational tasks violates project boundaries; projects have a defined lifecycle.

About these practice questions

One of 297 original PRINCE2-PRACTITIONER practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official AXELOS / PeopleCert exam blueprint

This PRINCE2-PRACTITIONER practice question is part of Courseiva's free AXELOS / PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2-PRACTITIONER exam.