CAPM Project Management Fundamentals and Core Concepts • Set 2
CAPM Project Management Fundamentals and Core Concepts Practice Test 2 — 15 questions with explanations. Free, no signup.
A project manager is leading a software development project. During the planning phase, the team identifies a significant risk that a key third-party API may be deprecated before the project completes. The project sponsor asks for a risk response strategy. Which strategy should the project manager recommend to best address this risk?