CAPM Project Management Fundamentals and Core Concepts • 10 Questions
10 CAPM Project Management Fundamentals and Core Concepts practice questions with answers and explanations. Free, no signup.
A project manager is reviewing the project charter and notices that the business case includes a cost-benefit analysis with a Net Present Value (NPV) of $50,000 and an Internal Rate of Return (IRR) of 12%. The company's required rate of return is 10%. What should the project manager conclude about this project?