PRINCE2F PRINCE2 Processes • Set 2
PRINCE2F PRINCE2 Processes Practice Test 2 — 15 questions with explanations. Free, no signup.
You are the project manager for a software development project following PRINCE2. The project is in its second stage, which has a budget tolerance of 10% above the planned cost of $200,000. The project board is composed of the executive, senior user, and senior supplier. The team has been working on a critical feature, but a key supplier has announced a 15% price increase for their services, effective immediately. This increase will push the stage costs to $230,000, exceeding the tolerance. The project manager must decide the best course of action. Which option should the project manager take?