PMP Process — Managing Technical Aspects Practice Question
Your project is in the execution phase. The earned value metrics are: EV=$200,000, PV=$250,000, AC=$220,000. The project is behind schedule and over budget. You need to present a recovery plan to the steering committee. Which combination of actions is BEST aligned with PMI best practices?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Conduct root cause analysis of variances, then consider fast tracking or crashing as appropriate.
The correct approach is to first perform root cause analysis to understand the reasons for the variances, then evaluate schedule compression techniques such as fast tracking or crashing. This aligns with PMI's guidance on taking corrective action. Option A is not sustainable and may not address root causes; option C requires formal change control and may not be the best first step; option D jumps to crashing without analysis and may escalate costs.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ask the team to work overtime without additional cost.
Why it's wrong here
This option is generally unsustainable and unethical as a primary response to project variances. Expecting overtime without compensation can lead to decreased morale, burnout, reduced productivity, and increased errors, ultimately exacerbating project issues rather than resolving them. Furthermore, it fails to address the underlying root causes of the schedule or cost deviations, making it a short-term, high-risk tactic that is not a PMP-recommended first step.
- ✓
Conduct root cause analysis of variances, then consider fast tracking or crashing as appropriate.
Why this is correct
This is the most appropriate PMP-aligned response. Before implementing any corrective actions, a thorough root cause analysis (RCA) is essential to understand why the project is deviating from its baselines. Only after identifying the true causes can effective and targeted strategies like fast tracking (performing activities in parallel) or crashing (adding resources to shorten duration) be considered and applied judiciously, ensuring the chosen method addresses the specific problem and aligns with project constraints.
- ✗
Reduce scope to meet the schedule and cost baselines.
Why it's wrong here
Reducing project scope is a significant change that directly impacts the project's deliverables and stakeholder value, making it an extreme measure. This action requires formal change control, including re-evaluation of business needs, stakeholder approval, and updates to the scope baseline, which is a complex and often undesirable process. It should only be considered as a last resort when other corrective actions are insufficient or infeasible, not as an initial response to variances.
- ✗
Crash the schedule by adding resources and request additional budget.
Why it's wrong here
Crashing the schedule is a valid schedule compression technique that involves adding resources to critical path activities to shorten their duration, often incurring additional cost. However, implementing crashing without first conducting a root cause analysis of the variances is premature and potentially wasteful. This approach assumes crashing is the optimal solution without understanding the underlying problem, which could lead to ineffective spending or even exacerbate issues if the root cause is not resource-related.
Go deeper
Related to this question
About these practice questions
One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.