Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

You are the project manager for a software development project using a hybrid approach. During a sprint review, the product owner requests a significant change to a feature that has already been accepted in a previous sprint. The change would require rework and impact the critical path. What should you do FIRST?

⚠ Common exam trap

The PMBOK Guide emphasizes that changes to baselines must go through formal change control. The trap here is that any change impacting the critical path must first go through formal change control to protect the project's baselines.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request and evaluate the impact on the project constraints

In a hybrid project, changes to accepted deliverables must follow a formal change control process. Submitting a change request (Option B) ensures the impact on the critical path, schedule, and budget is evaluated before any rework begins, aligning with the PMBOK Guide's guidance on integrated change control.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add the change to the product backlog for a future sprint without formal approval

    Why it's wrong here

    Even in agile, significant changes should go through change control when they impact baseline constraints.

  • Submit a change request and evaluate the impact on the project constraints

    Why this is correct

    This follows the Integrated Change Control process, which is the correct first step.

  • Instruct the team to implement the change immediately to maintain stakeholder satisfaction

    Why it's wrong here

    Implementing changes without formal approval bypasses change control, which PMI requires.

  • Reject the change because the feature was already accepted

    Why it's wrong here

    Rejecting without assessment is not proactive and ignores the stakeholder's need.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.