Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

You are managing a software development project using a hybrid approach. During a sprint review, the customer is delighted with the progress but requests a new feature that would require significant rework of the current sprint's deliverable. The feature is not in the backlog. What should you do FIRST?

⚠ Common exam trap

Many exam-takers assume agile principles allow immediate incorporation of customer feedback, but the hybrid approach requires formal change control when the change impacts a committed sprint deliverable, not just the backlog.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request, assess the impact on schedule and cost, and seek approval from the change control board

In a hybrid project management approach, changes that impact the current sprint's deliverable must be formally controlled. Submitting a change request allows you to assess the impact on schedule and cost before seeking approval from the change control board (CCB), ensuring that the change is evaluated against project constraints and stakeholder expectations. This aligns with the PMBOK Guide's integrated change control process, which is critical when a requested feature requires significant rework of an already-approved sprint deliverable.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Submit a change request, assess the impact on schedule and cost, and seek approval from the change control board

    Why this is correct

    This follows the Integrated Change Control process, which is the correct PMI approach.

  • Add the feature to the product backlog and prioritize it for the next sprint

    Why it's wrong here

    Adding without assessing impact and obtaining approval bypasses change control.

  • Inform the customer that no changes can be made at this stage

    Why it's wrong here

    Refusing without evaluation is not proactive and may miss valuable opportunities.

  • Work with the team to incorporate the feature immediately to maintain customer satisfaction

    Why it's wrong here

    Implementing without change control is gold-plating and violates the plan.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.