Courseiva
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

You are a project manager for a construction project that is experiencing delays due to unexpected soil conditions. The risk was identified and a contingency plan exists. Which TWO actions should you take?

⚠ Common exam trap

The PMP exam often tests the misconception that you should escalate or re-analyze when a risk occurs, but the correct approach is to execute the pre-planned contingency response first, then update the risk register.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement the contingency plan as documented in the risk register

The contingency plan was already documented in the risk register for this identified risk (unexpected soil conditions). When a risk occurs, the first action is to implement the pre-planned response as documented, which is a standard project management practice to minimize delay and avoid ad-hoc decisions. This aligns with the PMBOK Guide's guidance on executing risk responses for identified risks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Implement the contingency plan as documented in the risk register

    Why this is correct

    When a pre-identified risk materializes, the project manager's primary responsibility is to execute the pre-approved contingency plan. This plan, detailed in the risk register, represents the agreed-upon strategy developed during risk response planning. Implementing it promptly ensures a structured and efficient response, minimizing potential negative impacts on project objectives. This action demonstrates effective proactive risk management.

  • Contact the project sponsor to inform them of the delay and seek guidance

    Why it's wrong here

    While communicating significant project impacts to the sponsor is vital, it should not precede the implementation of an existing contingency plan. Seeking guidance for a situation that already has a documented response indicates a failure to act decisively on pre-approved strategies. The project manager should first execute the planned response and then inform stakeholders, including the sponsor, about the situation and the actions taken.

  • Immediately update the project baseline to reflect the delay

    Why it's wrong here

    Project baselines for scope, schedule, and cost are formal documents that serve as a reference point for performance measurement. Any modification to these baselines requires a formal change request and approval through the integrated change control process. Unilaterally updating a baseline without proper authorization undermines project control, configuration management, and the integrity of performance reporting.

  • Update the risk register with the actual impact and response taken

    Why this is correct

    After a risk event occurs and the contingency plan is implemented, it is crucial to update the risk register. This update should detail the actual impact of the risk, the effectiveness of the executed response, and any lessons learned from the event. Maintaining an accurate and current risk register is essential for ongoing risk monitoring, control, and for improving future project planning and organizational process assets.

  • Schedule a meeting with the team to discuss possible responses to the risk

    Why it's wrong here

    Convening a meeting to brainstorm responses for a risk that already has a documented contingency plan is an inefficient and inappropriate action. The project team has already invested time in developing and approving a specific response strategy for this identified risk. The project manager's role is to execute that pre-defined plan promptly, rather than delaying action by re-evaluating options.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.