Question 778 of 892
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is to document the issue in the issue log, evaluate alternative suppliers or workarounds, and communicate with stakeholders about the schedule impact. When a supplier delay threatens a critical path component and the planned response was to accept the risk, the project manager must shift from passive acceptance to active mitigation, because acceptance does not mean inaction—it means monitoring the risk and implementing a fallback or workaround once the risk materializes. On the PMP exam, this scenario tests your understanding of the Monitor Risks process and the distinction between risk acceptance and issue management; a common trap is choosing to wait passively for the supplier or escalating prematurely to the sponsor before exploring internal options. Remember the memory tip: Log it, Fix it, Tell it—capture the issue, find a workaround, then communicate the impact to stakeholders.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During project execution, a key supplier notifies you that they will be unable to deliver a critical component on time. This component is on the critical path. The risk was identified, and the response strategy was to accept the risk. Which THREE actions should you take? (Select exactly three.)

Question 1mediummulti select
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Document the issue in the issue log and update the risk register

The PM should first document the issue in the issue log (A), then evaluate alternatives to mitigate the delay (B), and communicate with stakeholders about the impact (D). Waiting for the supplier to resolve (C) is passive, and escalating to the sponsor (E) may be premature before exploring options.

Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Document the issue in the issue log and update the risk register

    Why this is correct

    Documenting is essential for tracking and transparency.

    Related concept

    Static NAT maps one inside address to one outside address.

  • Communicate the potential delay to key stakeholders and the project sponsor

    Why this is correct

    Stakeholders need to be informed of schedule impacts.

    Related concept

    Static NAT maps one inside address to one outside address.

  • Escalate the issue to the project sponsor for a decision

    Why it's wrong here

    Escalation may be needed later, but first the PM should attempt to manage the issue within their authority.

  • Wait for the supplier to provide a new delivery date before taking action

    Why it's wrong here

    Waiting is passive; the PM should take proactive steps.

  • Evaluate alternative suppliers or workarounds to minimize the schedule impact

    Why this is correct

    Proactively seeking solutions is recommended.

    Related concept

    Static NAT maps one inside address to one outside address.

Common exam traps

Common exam trap: NAT rules depend on direction and matching traffic

NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.

Detailed technical explanation

How to think about this question

NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.

KKey Concepts to Remember

  • Static NAT maps one inside address to one outside address.
  • PAT allows many inside hosts to share one public address using ports.
  • Inside local and inside global describe the private and translated addresses.
  • NAT ACLs identify traffic for translation, not always security filtering.

TExam Day Tips

  • Identify inside and outside interfaces first.
  • Check whether the scenario needs static NAT, dynamic NAT or PAT.
  • Do not confuse NAT matching ACLs with normal packet-filtering intent.

Key takeaway

NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Static NAT maps one inside address to one outside address..

What is the correct answer to this question?

The correct answer is: Document the issue in the issue log and update the risk register — The PM should first document the issue in the issue log (A), then evaluate alternatives to mitigate the delay (B), and communicate with stakeholders about the impact (D). Waiting for the supplier to resolve (C) is passive, and escalating to the sponsor (E) may be premature before exploring options.

What should I do if I get this PMP question wrong?

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

What is the key concept behind this question?

Static NAT maps one inside address to one outside address.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.