Question 476 of 892

Quick Answer

The correct choice is to explain the risks of skipping UAT and recommend following the project management plan. This response is grounded in the core principle that the project management plan, once baselined, serves as the authoritative guide for execution, and any deviation—especially one that eliminates a critical quality gate like user acceptance testing—must be evaluated for its impact on scope, quality, and stakeholder satisfaction. Skipping UAT directly violates the plan’s defined processes and exposes the project to undetected defects and unmet user requirements, which can lead to costly rework or outright rejection of deliverables. On the PMP exam, this scenario tests your understanding of the project manager’s ethical duty to protect the project’s integrity while maintaining a collaborative relationship with the sponsor; the common trap is to reflexively comply with the sponsor’s request or to escalate without first explaining the consequences. Remember the memory tip: “Plan first, risk second, change control third”—always anchor your response in the plan, communicate the risk, and then route any formal change through the integrated change control process.

PMP Practice Question: Business Environment: strategy and project benefits

This PMP practice question tests your understanding of business environment: strategy and project benefits. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a project's execution phase, the sponsor asks the project manager to skip the user acceptance testing (UAT) phase to save time and meet a tight deadline. What should the project manager do?

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the risks of skipping UAT and recommend following the project management plan.

Skipping UAT could lead to quality issues and unmet expectations. The project manager should explain the risks and recommend following the plan. Option A is incorrect because the sponsor's request should be handled through change control. Option B is reactive and may not prevent the issue. Option D bypasses the sponsor and may damage the relationship.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Explain the risks of skipping UAT and recommend following the project management plan. — Skipping UAT could lead to quality issues and unmet expectations. The project manager should explain the risks and recommend following the plan. Option A is incorrect because the sponsor's request should be handled through change control. Option B is reactive and may not prevent the issue. Option D bypasses the sponsor and may damage the relationship.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In a hybrid project, the project sponsor asks you to skip the testing phase to meet the deadline. The product is critical for an upcoming trade show. What should you do?

easy
  • A.Tell the sponsor that testing is mandatory and cannot be skipped
  • B.Explain the risks of skipping testing and propose reducing the scope of testing to high-risk areas only
  • C.Skip testing as requested to meet the deadline
  • D.Ask the quality assurance manager to decide

Why B: Option B is correct because the PM should explain the risks of skipping testing and propose alternatives that balance quality and schedule. Option A is wrong because skipping testing may lead to defects and reputational damage. Option C is wrong because the PM is responsible for quality and should not simply accept the request. Option D is wrong because it does not address the sponsor's concern.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.