- A
Analyze the budget variance and propose alternative cost-saving measures that minimize impact on quality
The PM should first understand the root cause of the overrun and propose informed alternatives.
- B
Implement a 10% across-the-board cost reduction on all activities
Why wrong: Across-the-board cuts may not address the actual issues and could harm critical tasks.
- C
Submit a change request to increase the budget
Why wrong: This should be considered after exploring cost-saving options.
- D
Agree to reduce testing as requested to stay within budget
Why wrong: Cutting testing may lead to quality issues and rework, increasing overall costs.
Quick Answer
The correct answer is to analyze the budget variance and propose alternative cost-saving measures that minimize impact on quality. This is correct because a project manager must balance the triple constraint—scope, time, and cost—without sacrificing the project’s value proposition; cutting testing or training without analysis can introduce severe quality risks, leading to costly rework and schedule delays. On the PMP exam, this scenario tests your understanding of integrated change control and stakeholder management, often appearing as a trap where the sponsor asks to cut testing or training to reduce budget, tempting you to accept a quick fix. The key is to remember that quality is a non-negotiable constraint, and any cost reduction must be data-driven. Memory tip: “Don’t cut the test, assess the rest”—always investigate the variance before slashing quality activities.
PMP People — Leading Projects Practice Question
This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your project is running 15% over budget at the midpoint. The sponsor asks you to cut costs by reducing the testing phase. What should you do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Analyze the budget variance and propose alternative cost-saving measures that minimize impact on quality
Option A is correct because as a project manager, your primary responsibility is to manage the project constraints while protecting the project's value. Reducing the testing phase without analysis could introduce significant quality risks, leading to rework or failure. Instead, you should analyze the budget variance to identify root causes and propose alternative cost-saving measures that minimize impact on quality, such as optimizing resource allocation or renegotiating vendor contracts.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Analyze the budget variance and propose alternative cost-saving measures that minimize impact on quality
Why this is correct
The PM should first understand the root cause of the overrun and propose informed alternatives.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Implement a 10% across-the-board cost reduction on all activities
Why it's wrong here
Across-the-board cuts may not address the actual issues and could harm critical tasks.
- ✗
Submit a change request to increase the budget
Why it's wrong here
This should be considered after exploring cost-saving options.
- ✗
Agree to reduce testing as requested to stay within budget
Why it's wrong here
Cutting testing may lead to quality issues and rework, increasing overall costs.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates may choose Option D (agree to reduce testing) because they mistakenly prioritize cost control over quality, forgetting that the PMP exam emphasizes protecting the project's value and managing stakeholder expectations through analysis and communication.
Detailed technical explanation
How to think about this question
In project management, the 'triple constraint' (scope, time, cost) is interconnected, and reducing one area without analysis often impacts others. A budget variance analysis involves comparing actual costs against the planned baseline (e.g., using Earned Value Management metrics like Cost Performance Index). Alternative cost-saving measures might include fast-tracking or crashing the schedule to reduce overhead, or using lower-cost resources for non-critical tasks, while preserving testing to maintain quality standards.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Analyze the budget variance and propose alternative cost-saving measures that minimize impact on quality — Option A is correct because as a project manager, your primary responsibility is to manage the project constraints while protecting the project's value. Reducing the testing phase without analysis could introduce significant quality risks, leading to rework or failure. Instead, you should analyze the budget variance to identify root causes and propose alternative cost-saving measures that minimize impact on quality, such as optimizing resource allocation or renegotiating vendor contracts.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
8 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A project is running 15% over budget at the midpoint. The sponsor is concerned and asks the PM to reduce costs by cutting team training and team-building activities. What should the PM do?
medium- A.Agree to cut training and team-building to meet the sponsor's request
- B.Reduce the project scope to cut costs
- ✓ C.Explain the importance of these activities and propose other cost-saving measures
- D.Escalate to the PMO for a decision
Why C: Option C is correct because the PM should protect the project's long-term success by explaining the critical role of team training and team-building in maintaining performance and morale, especially when the project is under budget pressure. Cutting these activities can lead to decreased productivity, higher turnover, and ultimately greater cost overruns. The PM should propose alternative cost-saving measures that do not compromise the team's capability or the project's quality.
Variation 2. Your project is running 15% over budget at the midpoint. The sponsor asks you to reduce costs by cutting the testing phase from three weeks to one week. What should you do FIRST?
medium- A.Agree to reduce testing, as the sponsor has authority over the budget
- B.Refuse the request, stating that testing is essential for quality
- ✓ C.Submit a change request to reduce testing and analyze the impact on quality and risks
- D.Implement the reduction immediately to save costs, then document it later
Why C: Option C is correct because the PMBOK Guide requires that any change to the project baseline, including scope, schedule, or budget, must follow the formal integrated change control process. The first step is to submit a change request to analyze the impact on quality, risks, and other constraints before making a decision. This ensures that the sponsor and stakeholders understand the trade-offs, such as increased defect risk or rework costs, before approving the reduction.
Variation 3. Your project is running 15% over budget at the midpoint. The sponsor asks you to skip the testing phase in the next sprint to save costs. The project follows a hybrid approach with both predictive and agile elements. What should you do?
hard- A.Reduce the scope of testing but not eliminate it entirely
- B.Inform the sponsor that testing cannot be skipped under any circumstances
- ✓ C.Perform a cost-benefit analysis and present alternative cost-saving measures to the sponsor
- D.Agree to skip testing to meet the sponsor's request
Why C: Option C is correct because, as a project manager, you must balance cost constraints with quality and risk. Skipping testing entirely introduces unacceptable technical debt and quality risks, especially in a hybrid project where testing is a critical control point. Performing a cost-benefit analysis allows you to objectively evaluate the impact of skipping testing and present data-driven alternatives, such as reducing test coverage in low-risk areas or deferring non-critical tests, while maintaining the integrity of the deliverable.
Variation 4. Your project is running 15% over budget at the midpoint. The sponsor asks you to reduce costs by cutting team training. Which TWO actions should you take?
medium- ✓ A.Analyze the budget to identify other areas where costs can be reduced without impacting quality
- B.Accept the sponsor's request and cancel all upcoming training
- C.Submit a change request to increase the budget
- D.Reduce the project scope to meet the budget
- ✓ E.Explain to the sponsor the benefits of training and the risks of cutting it
Why A: Option A is correct because it aligns with the project manager's responsibility to optimize the budget without compromising quality. By analyzing the budget, you can identify non-critical areas for cost reduction, such as administrative overhead or non-essential resources, while preserving team training which directly impacts long-term performance and quality. This approach demonstrates proactive cost management and stakeholder negotiation, key aspects of the 'People' domain in leading projects.
Variation 5. You are managing a project to develop a mobile app. The sponsor asks you to skip user acceptance testing (UAT) to meet an aggressive launch date. The team is concerned about quality risks. What should you do?
medium- A.Refuse the request without further discussion
- ✓ B.Explain the risks of skipping UAT and propose a change request to adjust the schedule
- C.Comply with the sponsor's request to meet the deadline
- D.Proceed with UAT secretly and report the launch date as planned
Why B: Option B is correct because the PM must communicate the risks of skipping UAT and follow proper change control. Option A is wrong because proceeding without sponsor awareness is unethical and risky. Option C is wrong because skipping UAT could lead to major defects post-launch. Option D is wrong because ignoring the sponsor's request without explanation may damage the relationship.
Variation 6. During a project status meeting, the sponsor asks you to skip the final round of testing to meet the original deadline, stating that the product is already 'good enough.' What is your best response?
medium- A.Agree to skip testing to maintain the schedule and stakeholder satisfaction
- B.Secretly continue testing but report that testing is complete
- C.Refuse outright and insist on completing all testing as planned
- ✓ D.Explain the risks of skipping testing and propose a formal change request to document the decision
Why D: The PM should explain the risks of skipping testing and suggest following the change control process if the schedule needs to be compressed. This upholds quality standards and PMI principles.
Variation 7. During a hybrid project, the project sponsor asks you to skip the testing phase in the next release to save time and meet an aggressive market deadline. The team is concerned about quality risks. What should you do FIRST?
hard- ✓ A.Discuss the risks of skipping testing with the sponsor and propose a compromise, such as risk-based testing
- B.Tell the team to add extra testing in the next sprint to compensate
- C.Escalate the issue to the PMO or steering committee for a decision
- D.Refuse the sponsor's request and insist on following the original plan
Why A: Option A is correct because, as a project manager, your first responsibility is to address the sponsor's request directly by communicating the quality risks and negotiating a balanced solution. Risk-based testing allows you to prioritize critical test cases, reducing overall testing time while still mitigating the highest-priority quality risks, which aligns with the hybrid project's need for both agility and governance.
Variation 8. During a project, the sponsor asks you to skip the testing phase to save time and meet the deadline. What should you do FIRST?
easy- ✓ A.Explain the risks of skipping testing and propose alternatives such as reducing scope or extending the schedule.
- B.Comply with the sponsor's request to meet the deadline.
- C.Ignore the request and continue as planned.
- D.Ask the quality assurance team to expedite testing.
Why A: Option A is correct because as a project manager, your first responsibility is to protect the project's value and quality. Skipping testing introduces significant technical debt and risk of undetected defects, which can lead to costly rework or failure. By explaining the risks and proposing alternatives like scope reduction or schedule extension, you demonstrate proactive stakeholder management and adherence to the PMI Code of Ethics and Professional Conduct.
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.