Question 276 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is that an SPI less than 1 and a CPI greater than 1 means the project is behind schedule but under budget. This interpretation stems directly from earned value management fundamentals: SPI measures schedule efficiency, where a value below 1.0 indicates less work has been completed than planned, while CPI measures cost efficiency, where a value above 1.0 indicates the work completed cost less than budgeted. On the Project Management Professional PMP exam, this specific combination tests your ability to read two metrics simultaneously without conflating them—a common trap is assuming both indices must move in the same direction. Remember that SPI and CPI are independent; you can be over budget and ahead of schedule, or, as here, under budget yet behind schedule. A quick memory tip: think of SPI as the “speedometer” (below 1 means slow) and CPI as the “wallet” (above 1 means money left over).

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is reviewing the schedule performance index (SPI) and cost performance index (CPI). The current values are SPI = 0.85 and CPI = 1.10. What is the most likely conclusion about the project?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "most likely"

    Why it matters: Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is behind schedule and under budget.

An SPI of 0.85 indicates the project is behind schedule (less than 1.0), while a CPI of 1.10 indicates the project is under budget (greater than 1.0). Therefore, the project is behind schedule but under budget, making option B correct.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is behind schedule and over budget.

    Why it's wrong here

    CPI > 1 means under budget, not over.

  • The project is behind schedule and under budget.

    Why this is correct

    SPI < 1 (behind schedule), CPI > 1 (under budget).

    Clue confirmation

    The clue word "most likely" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is ahead of schedule and over budget.

    Why it's wrong here

    SPI < 1 means behind schedule, not ahead.

  • The project is ahead of schedule and under budget.

    Why it's wrong here

    SPI < 1 means behind schedule.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often assume a project with a low SPI must also be over budget, but the CPI and SPI are independent metrics that can show different performance dimensions.

Detailed technical explanation

How to think about this question

The SPI is calculated as Earned Value (EV) divided by Planned Value (PV), and a value less than 1.0 means less work has been completed than planned. The CPI is EV divided by Actual Cost (AC), and a value greater than 1.0 means the project is spending less than budgeted for the work accomplished. In practice, this combination often occurs when the team is working efficiently but facing delays due to external dependencies or resource constraints.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is behind schedule and under budget. — An SPI of 0.85 indicates the project is behind schedule (less than 1.0), while a CPI of 1.10 indicates the project is under budget (greater than 1.0). Therefore, the project is behind schedule but under budget, making option B correct.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "most likely". Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.