Question 129 of 892
People — Leading ProjectshardMultiple SelectObjective-mapped

Quick Answer

The correct actions are to add the new features to the product backlog for consideration in a future sprint, have the product owner re-prioritize the backlog, and transparently communicate the impact of the change to stakeholders. This is because the sprint review is a time for inspection and adaptation, not for altering the current sprint’s scope; the sprint backlog is frozen once the sprint begins to protect the team’s commitment and velocity. On the PMP exam, this scenario tests your understanding of Scrum’s empirical process control and the product owner’s role in value-driven prioritization, often appearing as a trap where candidates mistakenly extend the sprint or allow unapproved work. The key memory tip is “Review, not revise”—the sprint review reviews the product increment, while scope changes go back to the product backlog for future prioritization.

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a sprint review, the product owner requests a significant scope change that would add two new features. The team estimates this would extend the sprint by one week. You are the Scrum Master. Which THREE actions should you take?

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Ask the product owner to prioritize the new features against existing backlog items

Option A is correct: the PO should prioritize. Option C is correct: the change should be added to the backlog and addressed in future sprints. Option E is correct: the impact should be communicated transparently. Option B is wrong because it violates the sprint commitment. Option D is wrong because the team should not work unapproved changes.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask the product owner to prioritize the new features against existing backlog items

    Why this is correct

    The PO owns the backlog and should prioritize based on value.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Instruct the team to start working on the new features immediately

    Why it's wrong here

    Starting work without formal acceptance violates sprint scope.

  • Agree to extend the sprint by one week to accommodate the changes

    Why it's wrong here

    Extending the sprint undermines timeboxing and the sprint goal.

  • Communicate the potential impact on the release plan to stakeholders

    Why this is correct

    Transparency about impacts is key in agile.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Add the new features to the product backlog for consideration in a future sprint

    Why this is correct

    New work should be added to the backlog and prioritized for later sprints.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Ask the product owner to prioritize the new features against existing backlog items — Option A is correct: the PO should prioritize. Option C is correct: the change should be added to the backlog and addressed in future sprints. Option E is correct: the impact should be communicated transparently. Option B is wrong because it violates the sprint commitment. Option D is wrong because the team should not work unapproved changes.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.