Question 492 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is to add the risk to the risk register, monitor it, and prepare a contingency plan. This is correct because a risk with 30% probability and $50,000 impact falls into the moderate category on a typical probability-impact matrix, where the expected monetary value of $15,000 is well within the $100,000 contingency reserve. For predictive project risk response, moderate probability and impact risks do not warrant active avoidance or transfer, but they do require a documented watch-and-prepare approach to ensure the contingency plan is ready if the risk materializes. On the PMP exam, this scenario tests your ability to match risk response strategies to the risk’s severity rather than overreacting to any single factor like probability or impact alone. A common trap is choosing a full mitigation or transfer response for a moderate risk, which wastes resources, or ignoring it entirely, which is reactive. Memory tip: think “Moderate = Monitor and Plan” — if the risk is not high enough to act on now, keep it on your radar with a backup ready.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Compare every option against the stated constraints before choosing — the best answer satisfies all requirements, not just the most obvious one. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is using a predictive lifecycle. The team has identified a potential risk that could cause a two-week delay. The risk has a probability of 30% and an impact of $50,000. The project has a contingency reserve of $100,000. What is the most appropriate risk response?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Add the risk to the risk register, monitor it, and prepare a contingency plan

Option A is correct: The risk is moderate; monitoring and preparing a contingency plan is appropriate. Option B is overly conservative, C is premature, D is reactive.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Transfer the risk to the customer through a contract clause

    Why it's wrong here

    This is a proactive response but may not be feasible or necessary for a moderate risk.

  • Accept the risk and take no further action, since the contingency reserve is sufficient

    Why it's wrong here

    Acceptance without monitoring is not best practice; at least monitor the risk.

  • Add the risk to the risk register, monitor it, and prepare a contingency plan

    Why this is correct

    For risks with moderate probability/impact, active monitoring and planning is appropriate.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Immediately allocate $50,000 from the contingency reserve to mitigate the risk

    Why it's wrong here

    Using contingency before the risk occurs is not recommended; reserve is for when the risk event happens.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Add the risk to the risk register, monitor it, and prepare a contingency plan — Option A is correct: The risk is moderate; monitoring and preparing a contingency plan is appropriate. Option B is overly conservative, C is premature, D is reactive.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

7 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project is in the planning phase. The team has identified 50 risks. The project manager wants to prioritize risks for further analysis. Which tool or technique is BEST suited for this?

medium
  • A.Risk register
  • B.SWOT analysis
  • C.Decision tree analysis
  • D.Probability and impact matrix

Why D: The probability and impact matrix is the best tool for prioritizing risks because it combines the likelihood of each risk occurring with its potential impact on project objectives, allowing the project manager to rank risks by their overall severity. This prioritization is essential during the planning phase to focus further qualitative or quantitative analysis on the most critical risks.

Variation 2. You are managing a project where a risk identified in the risk register has occurred. The risk response plan calls for mitigation, but the mitigation action will delay the critical path by 2 weeks. The project has no schedule reserve. What should the project manager do FIRST?

hard
  • A.Avoid implementing the risk response to protect the schedule
  • B.Use schedule compression techniques to offset the delay before implementing the response
  • C.Implement the risk response as planned and then submit a change request for the schedule delay
  • D.Escalate the issue to the project sponsor for a decision

Why C: Option C is correct: the PM should implement the risk response as planned, then assess the impact and submit a change request for any schedule changes. Option A is wrong because the response should be implemented. Option B is wrong because escalation is not needed yet. Option D is wrong because schedule compression should be considered after the impact is known.

Variation 3. A project manager is working on a predictive project. A team member identifies a risk that was not previously identified. The risk has a low probability but high impact. What should the PM do FIRST?

easy
  • A.Add the risk to the risk register and assess its impact
  • B.Escalate the risk to the project sponsor
  • C.Accept the risk because it has low probability
  • D.Implement a contingency plan immediately

Why A: Per PMI, any new risk should be documented in the risk register, and then the PM should plan a response. The first step is to add it to the register.

Variation 4. A project manager is reviewing the project's risk register and identifies several risks that could impact the project. According to PMBOK Guide, which THREE of the following are strategies for negative risks or threats? (Choose three.)

hard
  • A.Exploit
  • B.Enhance
  • C.Avoid
  • D.Transfer
  • E.Mitigate

Why C: Avoid, Transfer, and Mitigate are the three primary strategies for dealing with negative risks or threats as defined in the PMBOK Guide. Avoid involves eliminating the threat entirely by changing the project plan, Transfer shifts the impact of the threat to a third party (e.g., insurance, fixed-price contracts), and Mitigate reduces the probability or impact of the threat to an acceptable threshold. These strategies are specifically designed to address risks with a negative impact on project objectives.

Variation 5. The project team is in the process of identifying risks. Which tool or technique should the project manager use to identify risks?

easy
  • A.Quality audits
  • B.Earned value management
  • C.Brainstorming
  • D.Critical path method

Why C: Option A is correct: brainstorming is a common technique for risk identification. Options B, C, D are used in other processes.

Variation 6. Midway through your project, a key vendor informs you that they cannot deliver a critical component on time, which will impact the critical path. The risk was identified in the risk register with a 'mitigate' response. What should you do FIRST?

medium
  • A.Inform the sponsor of the delay and request additional budget
  • B.Issue a change request to update the project schedule
  • C.Implement the contingency plan that was developed for this risk
  • D.Meet with the vendor to negotiate an expedited delivery

Why C: Option A is correct: when a risk event occurs, the first step is to implement the agreed-upon risk response. Option B may be needed later but is not the immediate action. Option C bypasses the plan. Option D is reactive and unnecessary if the response is already planned.

Variation 7. You are the project manager for a large infrastructure upgrade project. The project involves deploying new servers across multiple data centers. During the execution phase, you receive a report that one of the critical servers has failed a security compliance test. The security team states that the server must be reconfigured and retested, which will take two days. However, this server is on the critical path and any delay will push the project completion date. Your sponsor is pressing you to meet the original deadline. The project has a contingency reserve for schedule risks. What is the best course of action?

hard
  • A.Instruct the team to skip the retest and proceed with deployment to meet the deadline.
  • B.Request additional funds from the management reserve to hire external consultants to resolve the issue faster.
  • C.Use the contingency reserve to cover the two-day delay and inform the sponsor that the schedule will be extended accordingly.
  • D.Implement schedule compression techniques such as fast tracking to recover the two days.

Why C: Option C is correct because the project has a contingency reserve specifically allocated for schedule risks, and the two-day delay caused by the security compliance failure is a known risk that the reserve is designed to cover. Using the contingency reserve allows the team to properly reconfigure and retest the server, ensuring security compliance without compromising project quality, while formally extending the schedule with sponsor awareness.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.