Question 689 of 892
People — Leading ProjectshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is to submit a change request to formally assess the impact on scope, schedule, and cost. This is correct because any new regulation that impacts project deliverables and the critical path triggers the integrated change control process, which requires a documented change request to evaluate the effects before any adjustments are made. Bypassing this formal step risks uncontrolled changes, schedule compression without approval, and non-compliance with governance. On the PMP exam, this scenario tests your understanding of the Perform Integrated Change Control process and the importance of following the change management plan, even under external pressure. A common trap is jumping to fast-track or crash the schedule without first assessing the impact through a change request. Remember the mnemonic “CR before CR” — always submit a Change Request before making any Critical path adjustments.

PMP People — Leading Projects Practice Question

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

In the middle of a project, a new regulation is introduced that impacts your project's deliverables. The team needs to make adjustments, but the change will affect the critical path. What should you do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1hardmultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to formally assess the impact on scope, schedule, and cost

Option B is correct because when a new regulation impacts project deliverables and the critical path, the first step is to submit a formal change request. This initiates the integrated change control process, ensuring that the impact on scope, schedule, and cost is assessed through a structured review before any action is taken. Bypassing this formal process risks uncontrolled changes and non-compliance with project governance.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the risk register and assess the impact on the critical path

    Why it's wrong here

    This is part of the analysis, but the first step should be initiating a change request.

  • Submit a change request to formally assess the impact on scope, schedule, and cost

    Why this is correct

    Following the change control process ensures proper evaluation and approval.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Direct the team to immediately implement the changes to ensure compliance

    Why it's wrong here

    Changes should go through formal assessment and approval first.

  • Inform the team to continue working as planned since the regulation may not be enforced

    Why it's wrong here

    Ignoring regulatory changes can expose the project to legal risks.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the immediate need to assess impact (Option A) with the formal first step of submitting a change request, failing to recognize that the change control process must be initiated before any analysis or action is taken.

Detailed technical explanation

How to think about this question

In project management, the change control system is a formal, documented process that governs how changes to the project baseline are proposed, evaluated, approved, and implemented. The critical path is the longest sequence of activities that determines the project's minimum duration; any change affecting it must be carefully analyzed for schedule compression or extension. Submitting a change request triggers a documented impact analysis, which includes assessing the regulation's effect on deliverables, re-estimating activity durations, and updating the project management plan only after formal approval.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit a change request to formally assess the impact on scope, schedule, and cost — Option B is correct because when a new regulation impacts project deliverables and the critical path, the first step is to submit a formal change request. This initiates the integrated change control process, ensuring that the impact on scope, schedule, and cost is assessed through a structured review before any action is taken. Bypassing this formal process risks uncontrolled changes and non-compliance with project governance.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.