Courseiva

PMP Practice Question: Business Environment: strategy and project benefits

In a hybrid project, the project sponsor asks you to skip the testing phase to meet the deadline. The product is critical for an upcoming trade show. What should you do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Explain the risks of skipping testing and propose reducing the scope of testing to high-risk areas only

The PM should explain the risks of skipping testing and propose alternatives that balance quality and schedule. Option A is wrong because it is overly rigid and does not engage the sponsor in a discussion about viable compromises; instead, it simply refuses without offering any alternative. Option C is wrong because the PM is responsible for quality and should not simply accept the request. Option D is wrong because it abdicates the PM's responsibility to manage stakeholder expectations and quality.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Tell the sponsor that testing is mandatory and cannot be skipped

    Why it's wrong here

    Simply stating that testing is mandatory dismisses the sponsor's request without engaging in collaborative problem-solving or exploring viable alternatives. This approach can damage crucial stakeholder relationships and indicates a lack of negotiation skills, which are essential for managing competing project constraints effectively. A Project Manager should seek to understand the sponsor's underlying concerns, such as schedule pressure, and then propose solutions that address those concerns while still upholding project objectives and quality standards.

  • Explain the risks of skipping testing and propose reducing the scope of testing to high-risk areas only

    Why this is correct

    This approach demonstrates effective project management by proactively addressing the sponsor's concern while safeguarding essential project quality. The Project Manager fulfills their responsibility to identify and communicate potential risks associated with reduced testing, such as increased defects or costly rework. By proposing a targeted testing strategy for high-risk areas, the PM collaborates with the sponsor to find a pragmatic compromise that balances schedule pressures with essential quality assurance, ensuring value delivery.

  • Skip testing as requested to meet the deadline

    Why it's wrong here

    Unilaterally skipping testing as requested is a significant abdication of the Project Manager's responsibility to protect project quality and manage project risks. This action can lead to severe negative consequences, including increased defects, costly rework, reputational damage, and potential project failure, ultimately undermining the project's value proposition. A Project Manager must prioritize long-term project success over short-term schedule adherence, especially when it compromises fundamental quality standards without proper assessment.

  • Ask the quality assurance manager to decide

    Why it's wrong here

    Delegating the decision to the quality assurance manager without providing analysis or a recommendation is an abdication of the Project Manager's accountability. While the QA manager is a subject matter expert on quality processes, the PM is ultimately responsible for making integrated project decisions that balance all constraints, including quality, schedule, and stakeholder expectations. The PM should leverage expert judgment but must present options and a reasoned recommendation to the sponsor for final approval, not simply pass the buck.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.