- A
Implement the pre-defined risk response as documented in the risk register.
The risk management plan contains the agreed response; implement it first.
- B
Inform the sponsor and ask for additional budget to expedite shipping.
Why wrong: This may be part of the response, but first follow the plan.
- C
Crash the schedule by adding extra resources to other tasks to recover time.
Why wrong: This is a schedule compression technique, but not the first step.
- D
Update the risk register and escalate to the steering committee.
Why wrong: Updating the register is needed, but first implement the response.
Quick Answer
The answer is to execute the predefined risk response as documented in the risk register. This is correct because the Project Management Professional PMP exam tests the principle that risk response execution must follow the risk management plan; when a risk occurs, you first implement the agreed-upon strategy rather than analyzing or escalating anew. The scenario tests your ability to trust the planning process—since the risk was identified and a response was already approved, deviating from it wastes time and introduces unnecessary uncertainty. A common trap on the exam is choosing to “analyze the impact” or “escalate to management” first, but those steps should have been completed during risk planning. Remember the memory tip: “Plan it, then play it”—if the response is already in the register, execute it immediately before considering alternatives.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your construction project is in the execution phase. A key vendor informs you that a critical material will be delayed by 3 weeks due to a strike at their factory. This delay will push the project beyond the required completion date. The risk was identified and documented in the risk register with a planned response. What should you do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Implement the pre-defined risk response as documented in the risk register.
The planned risk response should be executed as per the risk management plan. Option A is correct because the response is already defined. Option B is reactive; Option C skips the planned response; Option D may be needed later but is not first.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Implement the pre-defined risk response as documented in the risk register.
Why this is correct
The risk management plan contains the agreed response; implement it first.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Inform the sponsor and ask for additional budget to expedite shipping.
Why it's wrong here
This may be part of the response, but first follow the plan.
- ✗
Crash the schedule by adding extra resources to other tasks to recover time.
Why it's wrong here
This is a schedule compression technique, but not the first step.
- ✗
Update the risk register and escalate to the steering committee.
Why it's wrong here
Updating the register is needed, but first implement the response.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Implement the pre-defined risk response as documented in the risk register. — The planned risk response should be executed as per the risk management plan. Option A is correct because the response is already defined. Option B is reactive; Option C skips the planned response; Option D may be needed later but is not first.
What should I do if I get this PMP question wrong?
Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. You are the project manager for a large construction project. Midway through, a key supplier informs you that a critical component will be delayed by 6 weeks due to raw material shortages. The component is on the critical path and has zero float. What should you do FIRST?
hard- A.Terminate the contract with the supplier and find a new one
- B.Ask the team to work overtime to compress the schedule
- C.Notify the sponsor and stakeholders that the project will be delayed by 6 weeks
- ✓ D.Conduct a schedule impact analysis and evaluate options such as fast-tracking or crashing
Why D: Option B is correct because the first step is to assess the impact on the project schedule and explore options like fast-tracking or crashing. Option A is premature; Option C skips analysis; Option D is reactive and may not be optimal.
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.