Question 313 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is that the project is over budget and behind schedule. This conclusion is drawn from interpreting earned value metrics, specifically the cost performance index (CPI) and schedule performance index (SPI). CPI is calculated as EV divided by AC, yielding 50,000/70,000 = 0.71, which is less than 1.0 and indicates the project is over budget, as each dollar spent is only earning 71 cents of value. SPI is EV divided by PV, giving 50,000/60,000 = 0.83, also below 1.0, meaning the project is behind schedule, having completed only 83% of the planned work by this point. On the Project Management Professional PMP exam, this type of scenario tests your ability to quickly compute and interpret CPI and SPI from given data, often with a trap where candidates confuse the direction of the indices or misapply the formulas. A common memory tip is that both CPI and SPI should be greater than 1.0 for a healthy project; if either is below 1.0, the project is in trouble—think "below one, not much fun."

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project is halfway through its schedule. The earned value (EV) is $50,000, planned value (PV) is $60,000, and actual cost (AC) is $70,000. The project manager calculates the cost performance index (CPI) and schedule performance index (SPI). Based on these metrics, what is the most likely situation?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "most likely"

    Why it matters: Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget and behind schedule.

CPI = EV/AC = 50,000/70,000 = 0.71 (over budget), SPI = EV/PV = 50,000/60,000 = 0.83 (behind schedule). The project is both over budget and behind schedule.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is under budget but behind schedule.

    Why it's wrong here

    CPI < 1 indicates over budget.

  • The project is under budget and ahead of schedule.

    Why it's wrong here

    Both CPI and SPI are less than 1, indicating the opposite.

  • The project is over budget but ahead of schedule.

    Why it's wrong here

    SPI < 1 indicates behind schedule.

  • The project is over budget and behind schedule.

    Why this is correct

    CPI < 1 indicates over budget; SPI < 1 indicates behind schedule.

    Clue confirmation

    The clue word "most likely" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is over budget and behind schedule. — CPI = EV/AC = 50,000/70,000 = 0.71 (over budget), SPI = EV/PV = 50,000/60,000 = 0.83 (behind schedule). The project is both over budget and behind schedule.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Are there clue words in this question I should notice?

Yes — watch for: "most likely". Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.