Question 489 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is that the project is behind schedule and over budget. This conclusion is reached by calculating the Schedule Performance Index (SPI) as EV/PV, which equals 400,000/500,000 or 0.8, indicating work is progressing at only 80% of the planned rate, and the Cost Performance Index (CPI) as EV/AC, which equals 400,000/480,000 or approximately 0.83, meaning costs are exceeding the budgeted value of work performed. On the Project Management Professional PMP exam, this earned value analysis scenario tests your ability to interpret SPI and CPI values below 1.0 as negative performance indicators, a common trap where test-takers confuse the direction of the indices. A reliable memory tip is to remember that both SPI and CPI should be above 1.0 for a healthy project; if either is below 1.0, the project is in trouble—SPI below 1.0 means behind schedule, CPI below 1.0 means over budget.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is a construction project with a fixed price contract. At the 40% progress point, earned value (EV) is $400,000, actual cost (AC) is $480,000, and planned value (PV) is $500,000. What does this indicate?

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is behind schedule and over budget

Option A is correct because SPI = EV/PV = 400,000/500,000 = 0.8 (behind schedule), and CPI = EV/AC = 400,000/480,000 ≈ 0.83 (over budget). Options B and C have incorrect calculations. Option D is opposite.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is behind schedule and over budget

    Why this is correct

    SPI<1 and CPI<1 indicate schedule delay and cost overrun.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is ahead of schedule and under budget

    Why it's wrong here

    Both metrics are unfavorable.

  • The project is behind schedule but under budget

    Why it's wrong here

    CPI<1 indicates over budget, not under.

  • The project is ahead of schedule but over budget

    Why it's wrong here

    SPI<1 indicates behind schedule, not ahead.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is behind schedule and over budget — Option A is correct because SPI = EV/PV = 400,000/500,000 = 0.8 (behind schedule), and CPI = EV/AC = 400,000/480,000 ≈ 0.83 (over budget). Options B and C have incorrect calculations. Option D is opposite.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.