PMP Process — Managing Technical Aspects Practice Question

During project execution, a key supplier notifies you that they will be unable to deliver a critical component on time. This component is on the critical path. The risk was identified, and the response strategy was to accept the risk. Which THREE actions should you take? (Select exactly three.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Document the issue in the issue log and update the risk register

The correct actions are to document the issue in the issue log and update the risk register (A), communicate the delay to key stakeholders and sponsor (B), and evaluate alternative suppliers or workarounds to minimize schedule impact (E). These steps align with proactive risk management: first record the issue, then inform stakeholders, and finally explore alternatives to mitigate the delay. Option C (escalating to sponsor) is premature without first exploring options, and option D (waiting for supplier) is a passive approach that does not address the schedule risk.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Document the issue in the issue log and update the risk register

    Why this is correct

    Upon notification of a potential delay, the project manager must formally record this event. Documenting it in the issue log ensures it is tracked, assigned an owner, and managed to resolution. Simultaneously, updating the risk register is critical to reflect that a previously identified risk (supplier delay) has materialized, or to identify new secondary risks, and to reassess the overall project risk exposure. This systematic approach supports effective project control and communication.

  • Communicate the potential delay to key stakeholders and the project sponsor

    Why this is correct

    Proactive and timely communication is a cornerstone of effective project management. Informing key stakeholders and the project sponsor about a potential delay ensures transparency, manages expectations, and allows them to understand the potential impact on project objectives and benefits. This enables them to provide input, support decision-making, and prepare for any necessary adjustments, aligning with the "Plan Communications Management" process.

  • Escalate the issue to the project sponsor for a decision

    Why it's wrong here

    Immediately escalating the issue to the project sponsor for a decision is premature and bypasses the project manager's primary responsibility to analyze and attempt to resolve issues within their delegated authority. The project manager should first assess the impact, explore potential solutions, and develop recommendations before involving the sponsor. Escalation is reserved for issues that exceed the project manager's decision-making power or require higher-level intervention.

  • Wait for the supplier to provide a new delivery date before taking action

    Why it's wrong here

    Passively waiting for the supplier to provide a new delivery date before initiating any action is contrary to proactive project management principles. This approach wastes valuable time, potentially increasing the negative impact on the project schedule and budget. A project manager should immediately investigate the cause, assess the impact, and begin exploring alternative solutions or mitigation strategies to minimize disruption, rather than deferring action.

  • Evaluate alternative suppliers or workarounds to minimize the schedule impact

    Why this is correct

    Actively evaluating alternative suppliers or developing workarounds demonstrates proactive issue management and a commitment to minimizing project disruption. This involves exploring contingency plans, assessing new procurement options, or devising temporary solutions to maintain progress and mitigate the schedule impact. Such actions are crucial for maintaining project momentum and achieving objectives, aligning with the project manager's role in problem-solving and risk response.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.