PMP Process — Managing Technical Aspects Practice Question
During project execution, a key executive stakeholder bypasses you and gives direct instructions to the development team, causing confusion about priorities. What should you do FIRST?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Meet with the executive to discuss the importance of following the project communication plan
The PM should first address the issue directly with the executive stakeholder, explaining the impact of bypassing the project manager and reinforcing the communication plan. This is a proactive communication approach that aligns with PMI's stakeholder management principles.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the issue log and escalate the matter to the project sponsor
Why it's wrong here
This action is premature and bypasses the project manager's primary responsibility to directly address issues with the involved stakeholder. While documenting the issue in the issue log is a good practice for tracking, immediate escalation to the project sponsor should be reserved for situations where direct communication attempts have failed, or the issue's severity and impact clearly warrant higher-level intervention. Premature escalation can damage relationships and undermine the project manager's authority in resolving conflicts.
- ✓
Meet with the executive to discuss the importance of following the project communication plan
Why this is correct
This is the most appropriate initial response, demonstrating proactive stakeholder engagement and conflict resolution. Directly meeting with the executive allows the project manager to understand their perspective, educate them on the established communication protocols, and reinforce the project's governance structure. This approach aims to collaboratively resolve the communication breach, ensuring future adherence to the Communication Management Plan, which is crucial for maintaining project control, transparency, and preventing miscommunication or unauthorized changes.
- ✗
Instruct the team to ignore the executive's instructions
Why it's wrong here
Instructing the team to disregard an executive's instructions is highly unprofessional and counterproductive. This approach creates an adversarial environment, undermines the executive's authority, and can lead to team confusion, insubordination, or a breakdown in trust. The project manager's role is to address the root cause of the communication bypass directly with the executive through diplomatic means, rather than creating internal conflict or disrespecting senior leadership.
- ✗
Add the executive's requests to the change log and process them through change control
Why it's wrong here
While the executive's instructions might eventually necessitate a change request, the immediate and critical problem is the *method* of communication—bypassing established channels. Directly adding these requests to the change log without first addressing the communication breach implicitly validates the executive's inappropriate behavior and fails to reinforce project governance. The project manager must first address the process violation to ensure adherence to the Communication Management Plan before formally evaluating the content of the request via the Change Control Process.
Go deeper
Related to this question
About these practice questions
This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.