Courseiva
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

During project closure, the project manager is conducting lessons learned. The team identifies that poor communication with a remote team caused rework. Which THREE actions should the project manager take to ensure continuous improvement?

⚠ Common exam trap

Candidates often confuse updating the current project's communications management plan (Option A) as a valid continuous improvement action, but it is incorrect because the project is closing and improvements should be directed to future projects, not the current one.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the organizational process assets with the lessons learned

Updating organizational process assets (OPA) with lessons learned ensures that the knowledge gained from this project is formally captured and available for future projects, which is a key requirement for continuous improvement in project management. This aligns with the PMBOK Guide's emphasis on transferring lessons learned to the OPA to benefit the organization's project management processes. The other correct options (C and D) also support continuous improvement by documenting the lessons in the register and recommending improvements to the communications management plan for future projects.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the current project's communications management plan to prevent further issues

    Why it's wrong here

    During project closure, the project's execution phase is complete, rendering updates to the current project's communications management plan irrelevant. This plan is a component of the project management plan, which guides project execution. At closure, the focus shifts from guiding current work to formalizing completion, archiving information, and transferring knowledge, not revising active operational plans for a project that is concluding.

  • Update the organizational process assets with the lessons learned

    Why this is correct

    Updating organizational process assets (OPAs) with lessons learned is a critical activity during project closure. OPAs include organizational knowledge bases, templates, and procedures. Integrating these documented experiences ensures that the organization learns from its projects, preventing recurrence of issues and replicating successes, thereby fostering continuous improvement and enhancing future project performance.

  • Document the lessons learned in the project's lessons learned register

    Why this is correct

    Documenting lessons learned in the project's lessons learned register is a fundamental activity throughout the project lifecycle, and especially during closure. This register serves as a repository for insights gained regarding what went well, what could have been done better, and recommendations for future projects. It is a key output that feeds into the broader organizational process assets.

  • Recommend improvements to the communications management plan for future projects

    Why this is correct

    Recommending improvements to the communications management plan for future projects is a valuable output of the "Close Project or Phase" process. This activity involves analyzing the effectiveness of communication strategies employed and providing actionable feedback to refine organizational templates, policies, or procedures. This proactive approach contributes directly to enhancing the organization's project management methodology for subsequent endeavors.

  • Facilitate a conflict resolution session between the remote and local teams

    Why it's wrong here

    Facilitating a conflict resolution session addresses interpersonal friction after it has occurred, but the stem identifies poor communication as the root cause of rework, not unresolved conflict. The corrective action must implement a structured communication protocol—such as a defined cadence for status updates or a shared collaboration tool—to prevent recurrence. This option is tempting because conflict resolution is a valid team-building technique when personality clashes or misunderstandings have already disrupted workflow, but it does not establish the preventive process required for continuous improvement.

About these practice questions

This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.