Question 81 of 892
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is to add the risk to the risk register, but only after first assessing its probability and impact. This sequence is critical because the PMBOK Guide defines risk management as a continuous process where any new risk not in the risk register must be evaluated for its potential effect on project objectives before it can be prioritized and assigned a response. On the PMP exam, this tests your understanding of the "Identify Risks" and "Perform Qualitative Risk Analysis" processes in order; a common trap is to jump straight to creating a response plan or escalating the risk without the foundational assessment. Remember the memory tip: "Register it, rate it, respond to it"—you cannot skip the rating step. By first assessing the new risk, you ensure resources are allocated based on actual threat severity, preventing misinformed decisions that could derail the project schedule or budget.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a project, the team identifies a risk that could cause a significant delay. The risk is not in the risk register. Which THREE actions should the project manager take to respond appropriately?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Assess the probability and impact of the risk.

Option A is correct because when a new risk is identified, the project manager must first assess its probability and impact to understand the potential effect on project objectives. This assessment provides the data needed to prioritize the risk and determine an appropriate response. Without this evaluation, any subsequent actions would be uninformed and could misallocate resources.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Assess the probability and impact of the risk.

    Why this is correct

    Qualitative analysis is necessary to understand the risk.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Develop a risk response plan for the risk.

    Why this is correct

    After assessment, a response should be planned.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Ignore the risk because it was not identified during planning.

    Why it's wrong here

    Ignoring a risk is not a valid response.

  • Add the risk to the risk register.

    Why this is correct

    All identified risks should be documented in the risk register.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Immediately implement a risk response without assessment.

    Why it's wrong here

    The PM should first assess the risk before implementing a response.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may think they can skip the assessment step and go straight to developing a response, or that risks not in the register can be ignored, but PMI emphasizes that all risks must be formally assessed and documented before any response is implemented.

Detailed technical explanation

How to think about this question

In the PMBOK Guide, risk management is an iterative process; the risk register is a living document that should be updated throughout the project lifecycle. When a new risk is identified, the project manager follows the 'Identify Risks' process to add it to the register, then performs 'Perform Qualitative Risk Analysis' (and possibly 'Perform Quantitative Risk Analysis') to assess its characteristics. Only after this assessment should the 'Plan Risk Responses' process be executed to develop appropriate response plans. This sequence ensures that responses are proportional to the risk's severity.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Assess the probability and impact of the risk. — Option A is correct because when a new risk is identified, the project manager must first assess its probability and impact to understand the potential effect on project objectives. This assessment provides the data needed to prioritize the risk and determine an appropriate response. Without this evaluation, any subsequent actions would be uninformed and could misallocate resources.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.