- A
Update the risk register with the regulation as a new risk.
Why wrong: It is not a risk; it is a certainty that needs to be addressed.
- B
Inform the sponsor that the project will be delayed due to the new regulation.
Why wrong: The PM should first assess impact before informing.
- C
Analyze the impact of the regulation on scope, schedule, and cost, and then initiate a change request.
Assess impact first, then follow change control.
- D
Immediately implement the changes to comply with the regulation.
Why wrong: Changes should go through change control.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During a project, a new regulation is introduced that will affect the project's deliverables. The regulation is mandatory and will require changes to the scope. What should the project manager do first?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Analyze the impact of the regulation on scope, schedule, and cost, and then initiate a change request.
When a mandatory regulation impacts project deliverables, the project manager must first analyze the impact on scope, schedule, and cost to understand the full implications. This analysis provides the data needed to initiate a formal change request through the integrated change control process, ensuring the change is evaluated, approved, and documented before implementation. Option C correctly follows the PMBOK Guide's sequence of assess, then request change, rather than jumping to implementation or notification without analysis.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the risk register with the regulation as a new risk.
Why it's wrong here
It is not a risk; it is a certainty that needs to be addressed.
- ✗
Inform the sponsor that the project will be delayed due to the new regulation.
Why it's wrong here
The PM should first assess impact before informing.
- ✓
Analyze the impact of the regulation on scope, schedule, and cost, and then initiate a change request.
Why this is correct
Assess impact first, then follow change control.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Immediately implement the changes to comply with the regulation.
Why it's wrong here
Changes should go through change control.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse a mandatory external regulation with a risk, leading them to update the risk register (Option A) instead of recognizing it as a change that requires impact analysis and a formal change request.
Detailed technical explanation
How to think about this question
In the PMBOK Guide's process framework, the 'Perform Integrated Change Control' process requires that all changes, including those driven by external regulations, be evaluated for impact on the triple constraint (scope, time, cost) and submitted as a change request. The project manager uses tools like the scope baseline, schedule baseline, and cost baseline to perform this analysis, often employing a change control board (CCB) for approval. A real-world scenario might involve a new data privacy law (e.g., GDPR) that forces changes to a software project's data handling features; the PM must assess the effort and cost before requesting a formal change to the project plan.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Analyze the impact of the regulation on scope, schedule, and cost, and then initiate a change request. — When a mandatory regulation impacts project deliverables, the project manager must first analyze the impact on scope, schedule, and cost to understand the full implications. This analysis provides the data needed to initiate a formal change request through the integrated change control process, ensuring the change is evaluated, approved, and documented before implementation. Option C correctly follows the PMBOK Guide's sequence of assess, then request change, rather than jumping to implementation or notification without analysis.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.