During a project, a new regulation is introduced that will affect the project's deliverables. The regulation is mandatory and will require changes to the scope. What should the project manager do first?

⚠ Common exam trap

Candidates often confuse a mandatory external regulation with a risk, leading them to update the risk register (Option A) instead of recognizing it as a change that requires impact analysis and a formal change request.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact of the regulation on scope, schedule, and cost, and then initiate a change request.

When a mandatory regulation impacts project deliverables, the project manager must first analyze the impact on scope, schedule, and cost to understand the full implications. This analysis provides the data needed to initiate a formal change request through the integrated change control process, ensuring the change is evaluated, approved, and documented before implementation. Option C correctly follows the PMBOK Guide's sequence of assess, then request change, rather than jumping to implementation or notification without analysis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the risk register with the regulation as a new risk.

    Why it's wrong here

    A new regulation, once introduced, is a known event or condition, not an uncertain future event. Therefore, it is not classified as a risk to be managed in the risk register. Instead, it represents a new constraint or an issue that requires immediate assessment of its definite impact on project objectives and subsequent action through the change control process.

  • Inform the sponsor that the project will be delayed due to the new regulation.

    Why it's wrong here

    Informing the sponsor of a delay without prior impact analysis is premature and unprofessional. The Project Manager must first conduct a comprehensive assessment of the regulation's effects on scope, schedule, and cost to provide accurate, data-driven information. Communicating unverified assumptions can lead to unnecessary alarm and undermine stakeholder confidence.

  • Analyze the impact of the regulation on scope, schedule, and cost, and then initiate a change request.

    Why this is correct

    This is the correct project management approach. A new regulation represents a significant change that necessitates a comprehensive impact analysis across all project baselines, including scope, schedule, and cost. Following this assessment, a formal change request must be initiated to propose necessary adjustments, ensuring adherence to the integrated change control process and maintaining proper project governance.

  • Immediately implement the changes to comply with the regulation.

    Why it's wrong here

    Immediately implementing changes without proper assessment and formal approval through the integrated change control process is a critical governance failure. Such unilateral action can lead to uncontrolled scope creep, unapproved budget expenditures, and unmanaged schedule deviations, undermining project baselines and potentially violating organizational policies. All significant changes must be formally reviewed and approved.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.