Question 147 of 892
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is to implement a formal change control process and update the scope management plan. These two actions directly address scope creep control actions by establishing a documented, repeatable procedure for evaluating stakeholder requests before any work is done, and by clarifying the scope management plan to define how changes will be handled, approved, or rejected. On the Project Management Professional PMP exam, this scenario tests your understanding of the Plan Scope Management and Perform Integrated Change Control processes, often appearing as a situational question where informal requests have bypassed the change control board. A common trap is to choose only one action, such as simply saying "no" to stakeholders, but the PMBOK emphasizes that proactive control requires both a process and a plan. Remember the memory tip: "Process and Plan" — without both, scope creep will continue.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is experiencing scope creep due to informal requests from stakeholders. The project manager wants to establish better control. Which TWO actions should the project manager take?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement a formal change control process and educate stakeholders on how to submit change requests

Options B and E are correct: implementing a formal change control process and updating the scope management plan are proactive steps to control scope.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Politely decline all additional requests from stakeholders

    Why it's wrong here

    Declining all requests is not realistic; changes should be evaluated through a formal process.

  • Increase the project budget to accommodate potential changes

    Why it's wrong here

    Increasing budget without process does not prevent scope creep.

  • Ask the team to accommodate small requests without documentation if they are low effort

    Why it's wrong here

    Even small changes should be documented and approved to prevent scope creep.

  • Implement a formal change control process and educate stakeholders on how to submit change requests

    Why this is correct

    A formal process with stakeholder education helps manage changes properly.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Review and update the scope management plan to clarify how changes will be handled

    Why this is correct

    Updating the plan ensures everyone understands the process for scope changes.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Implement a formal change control process and educate stakeholders on how to submit change requests — Options B and E are correct: implementing a formal change control process and updating the scope management plan are proactive steps to control scope.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.