- A
Implement the change immediately without updating documents
Why wrong: Documents must be updated to maintain a record and manage future changes.
- B
Instruct the team to ignore the change until next sprint
Why wrong: Approved changes should be implemented as soon as possible, not delayed.
- C
File the change request in the project archives
Why wrong: Filing without updating plans means the change is not operationalized.
- D
Communicate the change to stakeholders and update the project management plan and baselines
Approved changes must be incorporated into plans and communicated to stakeholders.
Quick Answer
The answer is to communicate the change to stakeholders and update the project management plan and baselines. This is correct because once a change request is approved, especially one affecting the critical path, the project manager must formally integrate the change into the project’s governing documents to maintain alignment and control. The critical path defines the project’s minimum duration, so any approved change here requires immediate updates to the schedule baseline, cost baseline, and scope baseline, followed by stakeholder communication to ensure everyone works from the same revised plan. On the PMP exam, this tests your understanding of the Perform Integrated Change Control process and the sequence of actions after approval—a common trap is choosing “implement the change” first, but you must update the plan and baselines before execution. A helpful memory tip is “Plan First, Then Perform”: always update the project management plan and baselines immediately after approval, then communicate, then implement.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A change request that affects the critical path has been approved. What is the NEXT step for the project manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Communicate the change to stakeholders and update the project management plan and baselines
After approval, the PM must update the project management plan and baselines to reflect the change.
Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Implement the change immediately without updating documents
Why it's wrong here
Documents must be updated to maintain a record and manage future changes.
- ✗
Instruct the team to ignore the change until next sprint
Why it's wrong here
Approved changes should be implemented as soon as possible, not delayed.
- ✗
File the change request in the project archives
Why it's wrong here
Filing without updating plans means the change is not operationalized.
- ✓
Communicate the change to stakeholders and update the project management plan and baselines
Why this is correct
Approved changes must be incorporated into plans and communicated to stakeholders.
Related concept
Static NAT maps one inside address to one outside address.
Common exam traps
Common exam trap: NAT rules depend on direction and matching traffic
NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.
Detailed technical explanation
How to think about this question
NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.
KKey Concepts to Remember
- Static NAT maps one inside address to one outside address.
- PAT allows many inside hosts to share one public address using ports.
- Inside local and inside global describe the private and translated addresses.
- NAT ACLs identify traffic for translation, not always security filtering.
TExam Day Tips
- Identify inside and outside interfaces first.
- Check whether the scenario needs static NAT, dynamic NAT or PAT.
- Do not confuse NAT matching ACLs with normal packet-filtering intent.
Key takeaway
NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Static NAT maps one inside address to one outside address..
What is the correct answer to this question?
The correct answer is: Communicate the change to stakeholders and update the project management plan and baselines — After approval, the PM must update the project management plan and baselines to reflect the change.
What should I do if I get this PMP question wrong?
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
What is the key concept behind this question?
Static NAT maps one inside address to one outside address.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.