Question 835 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is to update the schedule baseline and inform all stakeholders of the approved change. This is correct because once the change control board (CCB) approves a scope increase, the project manager must formally integrate that change into the project management plan by updating the affected baseline—in this case, the schedule baseline to reflect the two-week delay—and then communicate the approved change to all relevant stakeholders per the Manage Communications process. On the PMP exam, this scenario tests your understanding of the Perform Integrated Change Control process and the sequence of steps after a change is approved; a common trap is to think the project manager should immediately implement the change without first updating the plan or to assume only the requester needs notification. Remember the memory tip: “Approve, Update, Inform”—the CCB approves, you update the baseline, then inform everyone.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a project, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will add two weeks to the schedule but no additional cost. The change request is approved by the change control board (CCB). What should the project manager do next?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the schedule baseline and inform all stakeholders of the approved change.

Option A is correct because, after the CCB approves a change that increases scope, the project manager must update the schedule baseline to reflect the approved two-week delay. This ensures the project plan remains accurate and serves as the basis for performance measurement. Informing all stakeholders of the approved change is a key communication requirement per the PMBOK Guide's Manage Communications process.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the schedule baseline and inform all stakeholders of the approved change.

    Why this is correct

    The schedule baseline is part of the project management plan and must be updated to reflect the change, then communicate.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Reject the change because it will delay the project.

    Why it's wrong here

    The change was approved by the CCB, so the PM must implement it.

  • Instruct the project team to begin working on the additional scope immediately.

    Why it's wrong here

    Working without updating the plan can lead to confusion and lack of documentation.

  • Update the work breakdown structure (WBS) and communicate the change to the project team.

    Why it's wrong here

    The WBS should be updated after the plan is updated, but the immediate next step is to update the schedule baseline.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the order of actions after CCB approval, mistakenly thinking that communicating to the team or updating the WBS should come before updating the schedule baseline, but the baseline must be formally revised first to maintain control over the project plan.

Trap categories for this question

  • Similar concept trap

    Working without updating the plan can lead to confusion and lack of documentation.

Detailed technical explanation

How to think about this question

Under the hood, the schedule baseline is a component of the project management plan that is formally controlled through integrated change control. Updating it involves recalculating the critical path and adjusting resource calendars to accommodate the two-week addition. In a real-world scenario, failing to update the baseline before communicating the change can lead to confusion in earned value management (EVM) calculations, where the planned value (PV) would no longer align with the approved schedule.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Update the schedule baseline and inform all stakeholders of the approved change. — Option A is correct because, after the CCB approves a change that increases scope, the project manager must update the schedule baseline to reflect the approved two-week delay. This ensures the project plan remains accurate and serves as the basis for performance measurement. Informing all stakeholders of the approved change is a key communication requirement per the PMBOK Guide's Manage Communications process.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.