Question 90 of 892
Business Environment: strategy and project benefitsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is to submit a change request to incorporate the regulatory requirements and assess the impact on schedule and budget. This is correct because when an audit finds non-compliance with regulation, the project manager must follow the formal integrated change control process to address the gap, as compliance is non-negotiable in a regulated industry. The change request documents the required data handling procedures and triggers a formal impact analysis on cost, schedule, and scope before any work begins. On the PMP exam, this tests your understanding that regulatory compliance is a constraint that overrides other priorities, but changes must still flow through the proper process rather than being implemented ad hoc. A common trap is choosing to stop work or inform the team informally, but the exam emphasizes that a change request is the first documented step. Memory tip: when an audit flags a gap, think "CR before action"—Change Request always comes first.

PMP Practice Question: Business Environment: strategy and project benefits

This PMP practice question tests your understanding of business environment: strategy and project benefits. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a project in a highly regulated industry. An audit reveals that your project is not fully compliant with a new data privacy regulation. The regulation requires specific data handling procedures that your team has not implemented. What should you do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to incorporate the regulatory requirements and assess impact on schedule and budget

The first step is to analyze the gap and submit a change request to implement the required procedures. Compliance is non-negotiable, but changes must follow the formal process.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Submit a change request to incorporate the regulatory requirements and assess impact on schedule and budget

    Why this is correct

    Following the change control process ensures that the impact is assessed and approved by the CCB.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Ignore the audit findings because the project is almost complete

    Why it's wrong here

    Ignoring compliance issues is unethical and could lead to severe consequences.

  • Immediately implement the required procedures to avoid legal penalties

    Why it's wrong here

    Implementing changes without change control bypasses governance, even for compliance.

  • Update the risk register and continue as planned until the regulation is enforced

    Why it's wrong here

    Waiting until enforcement could result in non-compliance; proactive action is required.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit a change request to incorporate the regulatory requirements and assess impact on schedule and budget — The first step is to analyze the gap and submit a change request to implement the required procedures. Compliance is non-negotiable, but changes must follow the formal process.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Your project is being audited for compliance with a new data protection regulation. The audit reveals several non-compliance issues. Which TWO actions should you take FIRST?

medium
  • A.Conduct a root cause analysis to understand why non-compliance occurred
  • B.Ignore the audit report until the project is complete
  • C.Escalate the audit findings to executive management immediately
  • D.Reassign the project team to different tasks to avoid further issues
  • E.Develop a remediation plan to address the non-compliance issues

Why A: Options B and D are correct. B: Analyzing the root cause helps prevent recurrence. D: Remediation plan is needed to address non-compliance. Option A is wrong because the PM should handle it without immediate escalation. Option C is wrong because ignoring the report is not acceptable. Option E is wrong because reassigning the team is not the first step.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.