Courseiva
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

An executive stakeholder bypasses you and directly gives instructions to the development team to add a new report. The team starts working on it. What should you do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Discuss with the executive the importance of following the change control process and update the communications management plan

PMI recommends addressing the stakeholder's behavior professionally and reinforcing the change control process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately stop the team's work on the new report without discussing with the executive

    Why it's wrong here

    Immediately stopping work without prior discussion with the executive stakeholder is a unilateral action that lacks proper communication and stakeholder engagement. This approach can lead to confusion, erode trust, and potentially cause unnecessary rework or delays if the executive's directive was critical, even if improperly delivered. A project manager should always seek clarification and follow established communication protocols before making such a drastic decision that impacts project scope and schedule.

  • Allow the team to continue to avoid conflict with the executive

    Why it's wrong here

    Allowing the team to continue working on an unapproved directive from an executive stakeholder directly undermines the project manager's authority and the established project governance framework. This inaction effectively condones scope creep, as the new report was not formally requested or approved through the change control process. Furthermore, it sets a dangerous precedent, encouraging other stakeholders to bypass formal channels, which can lead to uncontrolled project expansion and resource misallocation.

  • Confront the executive and demand they stop contacting the team

    Why it's wrong here

    Directly confronting the executive and demanding they cease contact with the team is an overly aggressive and unprofessional approach that risks severely damaging crucial stakeholder relationships. While the executive's action was improper, a confrontational stance escalates conflict rather than resolving the underlying process issue. Effective project management requires diplomacy and a focus on educating stakeholders about proper protocols, not issuing demands that alienate key project supporters.

  • Discuss with the executive the importance of following the change control process and update the communications management plan

    Why this is correct

    This is the most appropriate action because it addresses both the immediate issue and prevents future recurrences through proactive process improvement. Discussing the importance of the change control process educates the executive on proper project governance, ensuring all scope changes are formally evaluated and approved, thus maintaining project integrity. Simultaneously updating the communications management plan formalizes the correct channels for future directives, reinforcing proper stakeholder engagement and communication protocols for all project participants.

Go deeper

Related to this question

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.