Question 758 of 892
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is reviewing the project's risk register and identifies several risks that could impact the project. According to PMBOK Guide, which THREE of the following are strategies for negative risks or threats? (Choose three.)

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Avoid

Avoid, Transfer, and Mitigate are the three primary strategies for dealing with negative risks or threats as defined in the PMBOK Guide. Avoid involves eliminating the threat entirely by changing the project plan, Transfer shifts the impact of the threat to a third party (e.g., insurance, fixed-price contracts), and Mitigate reduces the probability or impact of the threat to an acceptable threshold. These strategies are specifically designed to address risks with a negative impact on project objectives.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Exploit

    Why it's wrong here

    Exploit is used to ensure an opportunity is realized.

  • Enhance

    Why it's wrong here

    Enhance is used to increase the probability or impact of an opportunity.

  • Avoid

    Why this is correct

    Avoid involves eliminating the threat or protecting the project from its impact.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Transfer

    Why this is correct

    Transfer involves shifting the impact of a threat to a third party.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Mitigate

    Why this is correct

    Mitigate involves reducing the probability or impact of a threat.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PMI often tests the confusion between threat and opportunity strategies, so the trap here is that candidates mistakenly select Exploit or Enhance because they sound like active responses, but they are reserved for positive risks, not threats.

Detailed technical explanation

How to think about this question

In risk management, the PMBOK Guide categorizes response strategies into two distinct groups: those for threats (negative risks) and those for opportunities (positive risks). The threat strategies—Avoid, Transfer, Mitigate, and Accept—each have specific mechanisms: Avoid might involve removing a high-risk vendor, Transfer might use a fixed-price contract to shift cost overruns, and Mitigate might add redundancy or conduct more testing. A common subtlety is that Accept is also a valid threat strategy, but it is not listed among the correct answers here because the question asks for three specific strategies from the provided set.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Avoid — Avoid, Transfer, and Mitigate are the three primary strategies for dealing with negative risks or threats as defined in the PMBOK Guide. Avoid involves eliminating the threat entirely by changing the project plan, Transfer shifts the impact of the threat to a third party (e.g., insurance, fixed-price contracts), and Mitigate reduces the probability or impact of the threat to an acceptable threshold. These strategies are specifically designed to address risks with a negative impact on project objectives.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.