PMP Process — Managing Technical Aspects Practice Question

A project manager is leading a construction project. The critical path has a total float of zero. A key supplier notifies you that a critical component will be delayed by two weeks, which will push the project beyond its deadline. The risk was identified and a mitigation plan exists. What should the PM do NEXT?

⚠ Common exam trap

The trap here is that candidates often jump to escalation or schedule compression without first executing the planned risk response, confusing the order of actions in the risk management process.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement the mitigation plan from the risk register

The risk was already identified and a mitigation plan exists in the risk register. The project manager should implement the mitigation plan as the next step, per the PMBOK Guide's risk response process, before escalating or changing the schedule. This ensures a proactive, planned response rather than a reactive or costly one.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Implement the mitigation plan from the risk register

    Why this is correct

    When a previously identified risk event materializes, the project manager's immediate and primary responsibility is to execute the pre-defined mitigation plan documented in the risk register. This proactive approach ensures that the project team leverages the planning efforts already invested, aiming to reduce the probability or impact of the adverse event. Implementing the planned response is the most efficient and effective way to manage known risks, aligning with best practices in risk management.

  • Immediately escalate the issue to the project sponsor

    Why it's wrong here

    Immediately escalating the issue to the project sponsor is generally premature. While escalation is a valid risk response strategy for risks exceeding the project manager's authority or impact threshold, it should typically occur only after the pre-defined mitigation plan has been attempted and proven insufficient, or if no plan exists. Bypassing the established risk response process can lead to unnecessary sponsor involvement and may undermine the project manager's accountability.

  • Accept the delay and update the project schedule

    Why it's wrong here

    Accepting the delay and updating the project schedule without first attempting the existing mitigation plan is a reactive and suboptimal approach. Acceptance, as a risk response strategy, is typically chosen when the cost of other responses outweighs the potential impact, or when no other viable response exists. Since a mitigation plan is already in place, the project manager has a responsibility to execute that plan before resorting to passive acceptance of the negative outcome.

  • Crash the schedule by adding resources to other tasks

    Why it's wrong here

    Crashing the schedule, which involves adding resources to shorten the project duration, is a schedule compression technique often used as a corrective action for delays. However, it typically incurs additional costs and may introduce new risks. While it could be a viable option, it should be considered as a secondary response or a workaround if the primary, pre-defined mitigation plan proves ineffective or if the risk was unanticipated. The first step for an identified risk is always to implement its planned response.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.