Scenario-based practice

Select Two (Multi-Select) Questions

Practise Program Management Professional (PgMP) (PgMP) practice questions — original exam-style scenarios covering every exam domain, with detailed explanations, wrong-answer analysis, and common exam traps.

20
scenario questions
PgMP
exam code
PMI
vendor

Scenario guide

How to approach select two (multi-select) questions

Multi-select questions tell you to 'Choose TWO' or 'Choose THREE'. Getting partial credit is not a thing — you must select all correct answers with no incorrect ones. The stem always states how many to choose, so trust it. These questions require precision, not best-guess elimination.

Quick answer

Select Two (Multi-Select) Questions questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Related practice questions

Related PgMP topic practice pages

Scenario questions usually connect to one or more exam topics. Use these links to review the underlying concepts behind the scenario.

Practice set

Practice scenarios

Question 1hardmulti select
Full question →

Which TWO actions should a program manager take to ensure successful benefit transition to operations?

Question 2hardmulti select
Full question →

You are leading a global program that involves stakeholders from multiple business units, external partners, and regulatory agencies. The program has entered a phase of significant scope changes. You need to update the stakeholder engagement strategy to maintain alignment and support. Which two actions should you take first? (Choose two.)

Question 3mediummulti select
Full question →

Which TWO factors should be considered when establishing the program governance structure?

Question 4easymulti select
Full question →

Which THREE of the following are benefits of a formal Program Closure process?

Question 5easymulti select
Full question →

Which TWO indicators show that stakeholder engagement is successful?

Question 6hardmulti select
Full question →

A program is entering its final benefits-realization phase. The program manager is updating the Stakeholder Engagement Plan to sustain commitment now that delivery work is winding down. Which TWO actions best support sustained stakeholder engagement during this phase? (Choose two.)

Question 7mediummulti select
Full question →

You are the program manager for a healthcare IT program. The Program Governance Board has asked you to establish a new program management office (PMO) to support governance activities. Which TWO responsibilities should the PMO have to ensure effective program governance? (Choose two.)

Question 8mediummulti select
Full question →

You are the program manager for a program that has just completed its first phase. The Program Governance Board (PGB) is conducting a phase-gate review. Which TWO items should the PGB review to determine whether the program should proceed to the next phase? (Choose two.)

Question 9mediummulti select
Full question →

A program manager is developing the benefits realization plan for a program that will deliver a new customer relationship management (CRM) system. The program manager needs to ensure that the plan includes appropriate elements for measuring and sustaining benefits. Which TWO elements should the program manager include? (Choose two.)

Question 10hardmulti select
Full question →

A program delivering a new claims processing platform has entered the benefits sustainment phase. The program manager observes that the expected reduction in processing cost per claim was achieved during the pilot but is now drifting back toward the pre-program baseline. Which two actions should the program manager take to address this drift? (Choose two.)

Question 11hardmulti select
Full question →

A program manager is preparing to transition a program from the Delivery phase into the Program Closure phase. The program has delivered all component outputs, but several benefits are still ramping toward their target measures. Which TWO activities are appropriate for the program manager to perform during this transition? (Choose two.)

Question 12hardmulti select
Full question →

A program manager is assessing whether a program that develops an artificial intelligence (AI)-based diagnostic tool for a hospital network remains strategically aligned. The organization's strategic plan now emphasizes value-based care and reducing diagnostic errors. The program's original business case focused on reducing radiology turnaround time. Which two actions should the program manager take to evaluate and maintain strategic alignment? (Choose two.)

Question 13mediummulti select
Full question →

A program manager is evaluating whether a program that develops a new customer relationship management (CRM) system is strategically aligned with the organization's goal to improve customer satisfaction. The program has three constituent projects: one for software development, one for data migration, and one for training. Which two criteria are most appropriate for assessing the strategic alignment of this program? (Choose two.)

Question 14mediummulti select
Full question →

A program manager is preparing the Stakeholder Engagement Plan for a program entering its second tranche. Several stakeholders have changed roles, a new regulatory body has emerged, and prior engagement assumptions no longer hold. Which TWO actions should the program manager take to ensure the plan remains valid? (Choose two.)

Question 15hardmulti select
Full question →

A program manager is planning the stakeholder engagement approach for a regulatory compliance program with a fixed external deadline. Two stakeholder groups have conflicting priorities: the legal department wants maximum controls and documentation, while the business units want minimal process disruption. Which TWO actions should the program manager take to manage this conflict constructively? (Choose two.)

Question 16hardmulti select
Full question →

A program manager is leading a complex program with stakeholders spread across multiple countries. The program manager wants to ensure that stakeholder engagement remains effective despite cultural differences. Which TWO actions should the program manager take to address cultural considerations in stakeholder engagement? (Choose two.)

Question 17mediummulti select
Full question →

Which TWO of the following are primary components of a Program Management Plan?

Question 18hardmulti select
Full question →

Which THREE of the following represent common challenges in program integration?

Question 19mediummulti select
Full question →

A program manager is developing the benefits realization plan for a program that will modernize a claims-processing platform. The sponsor wants assurance that the plan will support objective evaluation of whether the program delivered its intended value. Which two elements should the program manager include in the benefits realization plan to meet this expectation? (Choose two.)

Question 20mediummulti select
Full question →

A program governance board is reviewing the program's performance and wants to ensure that the governance framework is effectively supporting benefits realization. Which TWO actions should the program manager take to strengthen governance oversight? (Choose two.)