During program execution, the program manager identifies that two components have overlapping dependencies that are creating resource contention. Which TWO actions should the program manager take?
Trap 1: Direct the component managers to resolve the issue independently.
The program manager is responsible for interdependency management.
Trap 2: Escalate the issue to the Program Sponsor immediately.
Escalation is a last resort; the program manager should attempt resolution first.
Trap 3: Cancel one of the component projects.
Cancellation is not a standard response to resource contention.
- A
Direct the component managers to resolve the issue independently.
Why it fails: The program manager is responsible for interdependency management.
- B
Escalate the issue to the Program Sponsor immediately.
Why it fails: Escalation is a last resort; the program manager should attempt resolution first.
- C
Update the Program Resource Management Plan.
Overlapping dependencies causing resource contention must be resolved through the programme's resource governance. Updating the Program Resource Management Plan records the agreed reallocation and priority rules, giving the programme manager an approved baseline for arbitrating competing component demands during execution.
- D
Cancel one of the component projects.
Why it fails: Cancellation is not a standard response to resource contention.
- E
Re-evaluate component priorities via the Program Governance Board.
Escalating to the Program Governance Board lets it re-evaluate component priorities, resolving the overlapping dependencies driving resource contention. The board holds authority to arbitrate cross-component trade-offs, so prioritisation decisions realign resource allocation across the program, satisfying the stem's need to resolve contention between interdependent components.