A Program Governance Board (PGB) needs to escalate a cross-functional resource conflict that the Program Manager cannot resolve. What is the standard governance escalation path?
Trap 1: Escalate to the Program Manager's direct supervisor
This is an administrative escalation, not a governance resolution.
Trap 2: Escalate to the PMO Director
The PMO provides support but usually does not have authority over executive resource conflicts.
Trap 3: Escalate to the project sponsors
Project sponsors lack the authority to resolve cross-functional program-level conflicts.
- A
Escalate to the Program Manager's direct supervisor
Why it fails: This is an administrative escalation, not a governance resolution.
- B
Escalate to the PMO Director
Why it fails: The PMO provides support but usually does not have authority over executive resource conflicts.
- C
Escalate to the Program Steering Committee
The Program Steering Committee sits above the Program Manager and holds authority over cross-functional resource disputes that the PGB cannot settle internally. Escalating there satisfies the stem's constraint: a conflict the Program Manager has already failed to resolve, requiring governance-level arbitration beyond day-to-day program control.
- D
Escalate to the project sponsors
Why it fails: Project sponsors lack the authority to resolve cross-functional program-level conflicts.