Which of the following is considered a 'dis-benefit'?
Trap 1: A delay in project schedule.
This is a performance issue, not a business outcome.
Trap 2: The cost of the program.
Costs are investments, not necessarily negative outcomes.
Trap 3: A reduction in project scope.
This is a change control action.
- A
A delay in project schedule.
Why it fails: This is a performance issue, not a business outcome.
- B
The cost of the program.
Why it fails: Costs are investments, not necessarily negative outcomes.
- C
A reduction in project scope.
Why it fails: This is a change control action.
- D
Increased employee training requirements due to a new system.
Increased employee training requirements represent a negative outcome deliberately accepted in exchange for the new system's benefits. Unlike a risk, which is uncertain, a dis-benefit is a certain, realised consequence documented in the business case. This satisfies the stem's requirement by identifying a known drawback rather than a speculative threat.