Activity | Duration (days) | Predecessor
A | 3 | None
B | 5 | A
C | 4 | A
D | 6 | B, C
E | 2 | D

Refer to the exhibit. What is the critical path duration?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

16 days

The critical path is the longest path through the network. Path A-B-D-E: 3+5+6+2=16 days. Path A-C-D-E: 3+4+6+2=15 days. Therefore, the critical path duration is 16 days.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 14 days

    Why it's wrong here

    No path has a duration of 14 days.

  • 17 days

    Why it's wrong here

    No path has a duration of 17 days.

  • 16 days

    Why this is correct

    The critical path (A-B-D-E) totals 16 days.

  • 15 days

    Why it's wrong here

    This is the duration of the non-critical path.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.