Courseiva
Question 449 of 487
Predictive Plan-Based MethodologieshardMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A manufacturing project using predictive plan-based methodology is underway. The project manager identifies a risk that a key raw material supplier may go bankrupt, which would halt production for at least two weeks. The probability is assessed as 30% with a high impact. The project manager plans to hold a risk response planning meeting with the team. One team member suggests identifying an alternative supplier and signing a contingency contract. Another recommends self-insuring by setting aside budget reserves. The project sponsor wants to reduce the probability by investing in supplier financial health monitoring. Which combination of risk responses is MOST appropriate for this risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Transfer the risk by signing a contingency contract with an alternative supplier, and mitigate the risk by monitoring the supplier's financial health.

The correct combination is transferring the risk via a contingency contract with an alternative supplier and mitigating the risk by monitoring the supplier's financial health. Transfer involves shifting the financial impact to another party (the alternative supplier through a contingency contract), while mitigation reduces the probability or impact (monitoring financial health). Option B (stockpiling) is a form of mitigation but not mentioned in the stem, and cancelling the project (avoid) is too extreme. Option A suggests avoid by changing material (not feasible) and accept. Option D suggests accept and ignore, which is not appropriate for a high-impact risk.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Avoid the risk by choosing a different raw material, and accept the risk by setting aside contingency reserves.

    Why it's wrong here

    Avoiding may not be feasible without significant scope change.

  • Mitigate the risk by stockpiling raw materials, and avoid the risk by cancelling the project.

    Why it's wrong here

    Cancelling is extreme and not necessary.

  • Transfer the risk by signing a contingency contract with an alternative supplier, and mitigate the risk by monitoring the supplier's financial health.

    Why this is correct

    Contingency contract transfers the impact, monitoring reduces probability.

  • Accept the risk by using management reserves, and ignore mitigation efforts.

    Why it's wrong here

    Proactive responses are expected for high-impact risks.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.