Courseiva
Business Analysis FrameworkshardMultiple ChoiceObjective-mapped

CAPM Business Analysis Frameworks Practice Question

A global retail company is implementing a new e-commerce platform to replace a legacy system. The business analysis team has identified the following: The legacy system has been customized over 10 years, resulting in many undocumented business rules. The project timeline is aggressive (6 months), and the budget is fixed. The project sponsor insists on using an agile methodology to deliver quickly. The core team includes business analysts, developers, and testers, but the key business stakeholders (e.g., from merchandising, logistics, and customer service) are only available for one hour per week due to their operational roles. After the first sprint review, stakeholders expressed dissatisfaction that the delivered features do not match their expectations. The product owner is overwhelmed and struggles to prioritize the backlog. The business analysts notice that many requirements are still ambiguous and that the stakeholder feedback is inconsistent across different departments. The project is at risk of delivering a solution that does not meet business needs. What is the most effective course of action for the business analysts to take at this point?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Negotiate with the sponsor and stakeholders to extend the sprint duration to two weeks and require a minimum of three hours per week from key stakeholders

The root cause of the problem is insufficient stakeholder availability leading to poor requirements definition and inconsistent feedback. Extending the sprint duration to two weeks and requiring a minimum of three hours per week from key stakeholders directly addresses this by allowing more time for meaningful engagement and clarification. Option B (reducing scope) may help but does not resolve the core issue of stakeholder availability; it might still result in missing critical features. Option C (observation sessions) could uncover undocumented rules but does not directly improve stakeholder engagement in the iterative process. Option D (shifting to waterfall) conflicts with the sponsor's agile mandate and would not necessarily resolve the stakeholder availability constraint.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Negotiate with the sponsor and stakeholders to extend the sprint duration to two weeks and require a minimum of three hours per week from key stakeholders

    Why this is correct

    This increases stakeholder engagement, allowing for better requirements elicitation and validation.

  • Immediately reduce the project scope to the most essential features and accelerate the next sprint

    Why it's wrong here

    Reducing scope without resolving the requirements ambiguity will still result in unmet expectations.

  • Conduct a series of observation sessions in the stores and warehouses to uncover undocumented business rules

    Why it's wrong here

    While useful, observations require time and analysis; stakeholders are still needed to validate findings.

  • Request that the project sponsor approve a shift to a predictive (waterfall) lifecycle to define all requirements upfront

    Why it's wrong here

    This contradicts the agile mandate and may not be feasible given the timeline.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.