Courseiva

PRINCE2F Business Case and Organizing Practice Question

You are the project manager for a PRINCE2 project to develop a new mobile application. You are establishing the project's organization structure. According to PRINCE2, which TWO roles are part of the project board? (Choose two.)

⚠ Common exam trap

A common mix-up: candidates confuse project board roles with other project roles such as Project Manager or Team Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The project board in PRINCE2 consists of three core roles: Executive, Senior User, and Senior Supplier. The Executive represents the business, the Senior User represents the users, and the Senior Supplier represents the suppliers. These roles are accountable for the project's success. The Project Manager, Team Manager, and Project Assurance are not board members.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Assurance

    Why it's wrong here

    Project Assurance is a role that provides independent oversight of the project on behalf of the project board. They are not a member of the board themselves. They ensure that the project is being conducted properly and may report to the board. The board comprises the Executive, Senior User, and Senior Supplier. Project Assurance supports the board but does not have decision-making authority.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager is responsible for managing a team to produce products. They are not part of the project board. They report to the Project Manager and focus on delivering specialist products. The project board consists of the Executive, Senior User, and Senior Supplier. Team Managers may attend board meetings if invited, but they are not board members.

  • ✓

    Executive

    Why this is correct

    The Executive is a core role on the project board. They are accountable for the project's success and represent the business interest. They ensure the project delivers the required benefits and remains aligned with business strategy. The Executive chairs the project board and makes key decisions, such as approving the Business Case and authorizing stage boundaries.

  • ✓

    Senior User

    Why this is correct

    The Senior User is a core role on the project board. They represent the interests of those who will use the project's products and realize the benefits. They ensure that the project delivers the expected outcomes and benefits. The Senior User provides user requirements and monitors the solution's acceptance. They are accountable for benefits realization.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager is not a member of the project board. They manage the project on a day-to-day basis and report to the board. While they attend board meetings, they do not have voting rights. The board consists of the Executive, Senior User, and Senior Supplier. The Project Manager's role is to deliver the project within constraints.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.