PRINCE2F PRINCE2 Practices Practice Question
Who is responsible for the day-to-day management of project risks?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The Project Manager is responsible for the day-to-day management of risks, including maintaining the Risk Register and coordinating risk responses. Option A is wrong because the Executive owns the Business Case, not risk management. Option B is wrong because the Risk Actionee implements a specific risk response, not overall management. Option D is wrong because the Risk Owner is assigned for a specific risk and is accountable for its management, but the Project Manager handles day-to-day activities.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Executive
Why it's wrong here
The Executive does not manage risks day-to-day; that is the Project Manager's role.
- ✗
Risk Actionee
Why it's wrong here
The risk actionee implements a specific risk response, not overall risk management.
- ✓
Project Manager
Why this is correct
The Project Manager is responsible for ongoing risk management activities.
- ✗
Risk Owner
Why it's wrong here
The risk owner is responsible for managing a specific risk, not all project risks.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. In PRINCE2, which role is responsible for maintaining the risk register?
hard- A.The Senior User
- B.The Risk Owner
- C.The Project Assurance
- ✓ D.The Project Manager
Why D: The Project Manager is responsible for maintaining the risk register as part of the 'Manage Risk' practice. This includes ensuring that risks are recorded, updated, and reviewed throughout the project, and that the register reflects the current risk status. The Project Manager does not own individual risks but manages the register as a key project document.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.