Courseiva
PRINCE2 PracticeseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Who is responsible for the day-to-day management of project risks?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

The Project Manager is responsible for the day-to-day management of risks, including maintaining the Risk Register and coordinating risk responses. Option A is wrong because the Executive owns the Business Case, not risk management. Option B is wrong because the Risk Actionee implements a specific risk response, not overall management. Option D is wrong because the Risk Owner is assigned for a specific risk and is accountable for its management, but the Project Manager handles day-to-day activities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Executive

    Why it's wrong here

    The Executive does not manage risks day-to-day; that is the Project Manager's role.

  • Risk Actionee

    Why it's wrong here

    The risk actionee implements a specific risk response, not overall risk management.

  • Project Manager

    Why this is correct

    The Project Manager is responsible for ongoing risk management activities.

  • Risk Owner

    Why it's wrong here

    The risk owner is responsible for managing a specific risk, not all project risks.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In PRINCE2, which role is responsible for maintaining the risk register?

hard
  • A.The Senior User
  • B.The Risk Owner
  • C.The Project Assurance
  • D.The Project Manager

Why D: The Project Manager is responsible for maintaining the risk register as part of the 'Manage Risk' practice. This includes ensuring that risks are recorded, updated, and reviewed throughout the project, and that the register reflects the current risk status. The Project Manager does not own individual risks but manages the register as a key project document.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.