Courseiva
Project Initiation and StageshardMultiple SelectObjective-mapped

PRINCE2F Project Initiation and Stages Practice Question

Which TWO statements about the Initiating a Project process are correct?

⚠ Common exam trap

PeopleCert often tests the distinction between what happens during Initiating a Project versus Starting Up a Project, specifically that the project plan is created during initiation (not after) and that the Project Board, not the project manager, authorizes the project to proceed.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The business case is refined and approved by the project board

The Initiating a Project process includes refining the Business Case based on more detailed information gathered during initiation, and the Project Board reviews and approves it to confirm the project's viability. This ensures the project remains aligned with corporate objectives before proceeding.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project plan is created after the Initiating a Project process

    Why it's wrong here

    The project plan is created during Initiating a Project.

  • The project manager authorizes the project to proceed

    Why it's wrong here

    Authorization comes from the project board.

  • The approach to tailoring PRINCE2 is decided after the project is initiated

    Why it's wrong here

    Tailoring is decided during initiation.

  • The business case is refined and approved by the project board

    Why this is correct

    The business case is updated and approved in this process.

  • The project initiation documentation (PID) is assembled and reviewed

    Why this is correct

    The PID is a key output of this process.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which role is responsible for approving the Project Initiation Documentation?

easy
  • A.Project Board
  • B.Senior User
  • C.Project Manager
  • D.Senior Supplier

Why A: The Project Board is responsible for approving the Project Initiation Documentation (PID) because it represents the collective authority of the business, user, and supplier interests. The PID formally authorizes the initiation of the project and commits resources, so only the Project Board has the necessary authority to approve it.

Variation 2. A project manager is creating the Project Initiation Documentation. Which document must be produced before the Initiation Stage can be considered complete?

easy
  • A.Business Case
  • B.Project Initiation Documentation
  • C.Project Plan
  • D.Risk Register

Why B: In PRINCE2, the Project Initiation Documentation (PID) is the key deliverable of the Initiation Stage. The stage is not considered complete until the PID has been created and approved, as it provides the foundation for project governance and decision-making. The Business Case, Project Plan, and Risk Register are all components that are assembled into the PID, but the PID itself is the definitive document that marks stage completion.

Variation 3. Who is responsible for creating the Project Initiation Documentation?

easy
  • A.Project Board
  • B.Senior Supplier
  • C.Project Manager
  • D.Senior User

Why C: The Project Manager is responsible for creating the Project Initiation Documentation (PID) because PRINCE2 assigns the Project Manager the role of assembling and producing the PID, which consolidates key planning documents like the Business Case, Project Plan, and Risk Register. The Project Board approves the PID, but does not create it, as the Project Manager acts as the single point of accountability for its preparation and quality.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.