- A
Team Manager
Why wrong: Team Managers are not on the Project Board.
- B
Project Manager
Why wrong: The Project Manager reports to the Board but is not a member.
- C
Senior User
The Senior User is a member of the Project Board.
- D
Executive
The Executive is a member of the Project Board.
- E
Project Support
Why wrong: Project Support is not on the Project Board.
Quick Answer
The answer is the Executive and the Senior User. These two roles, along with the Senior Supplier, form the mandatory Project Board in PRINCE2, which acts as the project’s decision-making body. The Executive owns the business case and holds ultimate authority, while the Senior User represents the end users and ensures the project delivers the expected benefits. On the PRINCE2 Foundation exam, this concept tests your understanding of governance structure, often appearing in questions that ask you to identify which roles are accountable for key decisions versus those that are advisory. A common trap is confusing the Project Manager or Project Assurance with board members, but remember that the board is strictly the Executive, Senior User, and Senior Supplier. To lock this in, use the mnemonic “Eat, Sleep, Use” for Executive, Senior Supplier, and Senior User—the three seats at the board table.
PRINCE2F PRINCE2 Practices Practice Question
This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO roles are part of the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Senior User
The Project Board is the decision-making body of a PRINCE2 project, and its mandatory roles are the Executive, Senior User, and Senior Supplier. The Senior User (Option C) is correct because they represent the interests of those who will use the project's outputs and are responsible for specifying requirements and ensuring the project delivers the expected benefits. The Executive (Option D) is correct as they own the business case and have ultimate authority over the project.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team Manager
Why it's wrong here
Team Managers are not on the Project Board.
- ✗
Project Manager
Why it's wrong here
The Project Manager reports to the Board but is not a member.
- ✓
Senior User
Why this is correct
The Senior User is a member of the Project Board.
Related concept
Read the scenario before looking for a memorised answer.
- ✓
Executive
Why this is correct
The Executive is a member of the Project Board.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Project Support
Why it's wrong here
Project Support is not on the Project Board.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PeopleCert often tests the distinction between management roles (Project Board) and delivery/administrative roles (Team Manager, Project Support), leading candidates to mistakenly include the Project Manager as a Board member because they are the most visible role in project execution.
Detailed technical explanation
How to think about this question
Under PRINCE2, the Project Board is responsible for key decisions such as approving stage plans, reviewing the business case, and authorizing project closure. The Executive chairs the Board and is accountable for the project's success, while the Senior User ensures the final product meets user needs and that benefits are realized. In a real-world scenario, if a project fails to deliver expected benefits, the Senior User is held accountable for not clearly defining requirements or accepting outputs that do not meet user needs.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
PRINCE2 Practices — study guide chapter
Learn the concepts, then practise the questions
- →
PRINCE2 Practices practice questions
Targeted practice on this topic area only
- →
All PRINCE2F questions
1,731 questions across all exam domains
- →
PRINCE2 Foundation study guide
Full concept coverage aligned to exam objectives
- →
PRINCE2F practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PRINCE2F practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Overview of PRINCE2 and Principles practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and Principles.
Business Case and Organizing practice questions
Practise PRINCE2F questions linked to Business Case and Organizing.
Project Initiation and Stages practice questions
Practise PRINCE2F questions linked to Project Initiation and Stages.
Overview of PRINCE2 and the project environment practice questions
Practise PRINCE2F questions linked to Overview of PRINCE2 and the project environment.
People: organizations, teams, and leadership practice questions
Practise PRINCE2F questions linked to People: organizations, teams, and leadership.
PRINCE2 Practices practice questions
Practise PRINCE2F questions linked to PRINCE2 Practices.
PRINCE2 Processes practice questions
Practise PRINCE2F questions linked to PRINCE2 Processes.
PRINCE2F fundamentals practice questions
Practise PRINCE2F questions linked to PRINCE2F fundamentals.
PRINCE2F scenario practice questions
Practise PRINCE2F questions linked to PRINCE2F scenario.
PRINCE2F troubleshooting practice questions
Practise PRINCE2F questions linked to PRINCE2F troubleshooting.
Practice this exam
Start a free PRINCE2F practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PRINCE2F question test?
PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Senior User — The Project Board is the decision-making body of a PRINCE2 project, and its mandatory roles are the Executive, Senior User, and Senior Supplier. The Senior User (Option C) is correct because they represent the interests of those who will use the project's outputs and are responsible for specifying requirements and ensuring the project delivers the expected benefits. The Executive (Option D) is correct as they own the business case and have ultimate authority over the project.
What should I do if I get this PRINCE2F question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
6 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which THREE of the following are roles on the Project Board?
medium- ✓ A.Senior Supplier
- B.Project Support
- ✓ C.Senior User
- ✓ D.Executive
- E.Project Manager
Why A: The Project Board consists of Executive, Senior User, and Senior Supplier.
Variation 2. Which TWO of the following are typical roles in the Project Board?
medium- ✓ A.Senior Supplier
- B.Project Manager
- C.Team Manager
- D.Project Support
- ✓ E.Executive
Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. Senior Supplier is part of the Board; Project Manager is not on the Board.
Variation 3. Which TWO roles are permanent members of the Project Board?
easy- ✓ A.Executive
- B.Team Manager
- ✓ C.Senior User
- D.Project Manager
- E.Project Support
Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. The Project Manager is not a permanent member.
Variation 4. Which TWO roles are members of the Project Board?
medium- ✓ A.Executive
- B.Project Manager
- ✓ C.Senior Supplier
- D.Team Manager
- E.Project Support
Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. The Project Manager and Team Manager are not board members.
Variation 5. Which TWO are roles that are part of the Project Board?
easy- A.Project Manager
- B.Project Assurance
- C.Team Manager
- ✓ D.Senior User
- ✓ E.Executive (Senior Responsible Owner)
Why D: The Project Board consists of Executive (Senior Responsible Owner), Senior User, and Senior Supplier.
Variation 6. Which TWO roles are part of the Project Board?
medium- ✓ A.Senior User
- ✓ B.Executive
- C.Project Manager
- D.Team Manager
- E.Change Authority
Why A: The Project Board consists of the Executive, Senior User, and Senior Supplier. Therefore, options A and B are correct. Option C is wrong because the Project Manager is not on the Board. Option D is wrong because Change Authority is a separate role. Option E is wrong because the Team Manager reports to the Project Manager.
Last reviewed: Jun 30, 2026
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.